(1) Establishment of Procedures . The Office of the Inspector General shall establish procedures that specify the requirements and conditions that an awarding authority must meet to be issued a Notice to Proceed.
Content of Procedures. The Procedures shall include the standards as prescribed by the Inspector General that an awarding authority must meet to obtain a notice to proceed, the policies that the Office of the Inspector General will use in a review of the application to proceed, and the specific procedures that an awarding authority must follow to obtain a notice to proceed.
(2) General Information . The Procedures shall include general information on the construction management at risk delivery method of public construction.