Section 8.05 - Correction of Update Statements

Current through Register 1531, September 27, 2024

(1) Matters of Form. An Awarding Authority shall not reject a Contractor's bid because there are mistakes or omissions of form in the Update Statement submitted with the Contractor's bid pursuant to M.G.L. c. 149, § 44D, provided the Contractor promptly corrects those mistakes or omissions upon request of the Awarding Authority.

(2) Correction of Other Defects. An Awarding Authority may, in its discretion, give a Contractor notice of non-material errors and omissions in the Contractor's Update Statement and provide an opportunity to correct its Update Statement. However, the Contractor shall not be allowed to make corrections to an Update Statement in the event of material errors or omissions filed in the Update Statement with the Contractor's bid. The Awarding Authority shall advise DCAM of any material erroneous statements or omissions in a Contractor's Update Statement.

Disclaimer: These regulations may not be the most recent version. Massachusetts may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.