Construction documents shall be in accordance with sections R107.2.1 through R107.2.9.
R107.2.1 Information on Construction Documents. Construction documents shall be drawn upon suitable material. Electronic media documents are permitted to be submitted where approved by the building official. Construction documents shall be of sufficient clarity to indicate the location, nature and extent of the work proposed and show in detail that it will conform to the provisions of 780 CMR and relevant laws, ordinances, rules and regulations, as determined by the building official.
R107.2.2 - Reserved
R107.2.3 Means of Egress. The construction documents shall designate the two required exit door locations. Although not a portion of a Means of Egress, the construction documents shall show any Emergency Escape and Rescue Opening elements, when applicable.
R107.2.4 Reserved
R107.2.5 Energy Compliance submittal. The construction documents submitted with the application for permit shall be accompanied by completed energy code compliance documentation demonstrating compliance with the energy provisions of 780 CMR R11.00: Energy Efficiency (as amended by Massachusetts).
R107.2.6 Information on Braced Wall Design. For buildings and structures utilizing braced wall design, the braced wall lines shall be identified on the construction documents when required by the building official. Pertinent information including, but not limited to, bracing methods, location and length of braced wall panels and foundation requirements of braced wall panels at top and bottom shall be provided.
R107.2.7 Information for Construction in Flood Hazard Areas. For buildings and structures located in whole or in part in flood hazard areas as established by Table R301.2(1), construction documents shall include:
R107.2.8 Manufactured Buildings and Modular Homes. Document submittal for the erection or placement of said structures shall be as follows:
EXCEPTION: If all connection details are provided on the plans then the set manual is not required.
In accordance with 780 CMR Chapter 110.R3.8.1.1 and 110.R5.1.3.1 a "Homeowner exemption" may not be utilized to receive a permit to install, erect, or oversee the installation of a Manufactured Building or Modular Home.
R107.2.9 Site Plan or Plot Plan. The construction documents submitted with the application for permit shall be accompanied by a site plan showing to scale the size and location of new construction and existing structures on the site, distances from lot lines, the established street grades and the proposed finished grades and, as applicable, flood hazard areas, floodways, and design base flood elevations; and it shall be drawn in accordance with an accurate boundary line survey. In the case of demolition, the site plan shall show construction to be demolished and the location and size of existing structures and construction that are to remain on the site or plot. The building official is authorized to waive or modify the requirement for a site plan where the application for permit is for alteration or repair or where otherwise warranted.