R402.1.5.1 Add the section as follows:

R402.1.5.1 Approved software for Total UA alternative: The following software is approved for demonstrating Total UA compliance: REScheck-Web available at http://www.energycodes.gov/rescheck

R402.4.1.1 Amend Table R402.4.1.1 as follows:

TABLE R402.4.1.1

AIR BARRIER AND INSULATION INSTALLATION

COMPONENT

AIR BARRIER CRITERIA

INSULATION INSTALLATION CRITERIA

General requirements

A continuous air barrier shall be installed in the building envelope. The exterior thermal envelope contains a continuous air barrier. Breaks or joints in the air barrier shall be sealed.

All insulation shall be installed at Grade I quality in accordance with ICC/RESNET 301.

R403.3.5 Amend as follows:

R403.3.5 Duct testing. Ducts shall be pressure tested in accordance with ANSI/RESNET/ICC 380 or ASTM E1554 to determine air leakage by one of the following methods:

1. Rough-in test: Total leakage shall be measured with a pressure differential of 0.1 inch w.g. (25 Pa) across the system, including the manufacturer's air handler enclosure if installed at the time of the test. Registers shall be taped or otherwise sealed during the test.

2. Postconstruction test: Total leakage shall be measured with a pressure differential of 0.1 inch w.g. (25 Pa) across the entire system, including the manufacturer's air handler enclosure. Registers shall be taped or otherwise sealed during the test.

Postconstruction or rough-in testing and verification shall be done by a HERS Rater, HERS Rating Field Inspector, or an applicable BPI Certified Professional. A written report of the results of the test shall be signed by the party conducting the test and provided to the code official.

Exception: A duct air-leakage test shall not be required for ducts serving heating, cooling or ventilation systems that are not integrated with ducts serving heating or cooling systems.

Disclaimer: These regulations may not be the most recent version. Massachusetts may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.