Subsection 1913.9 - Curing
Current through Register 1531, September 27, 2024
During the curing periods specified herein, shotcrete shall be maintained above 40°F (4°C) and in moist condition.
1913.9.1 Initial curing. Shotcrete shall be kept continuously moist for 24 hours after shotcreting is complete or shall be sealed with an approved curing compound.
1913.9.2 Final curing. Final curing shall continue for seven days after shotcreting, or for three days if high- early-strength cement is used, or until the specified strength is obtained. Final curing shall consist of the initial curing process or the shotcrete shall be covered with an approved moisture-retaining cover.
1913.9.3 Natural curing. Natural curing shall not be used in lieu of that specified in this section unless the relative humidity remains at or above 85 percent, and is authorized by the registered design professional and approved by the building official.