Code of Massachusetts Regulations
780 CMR - STATE BOARD OF BUILDING REGULATIONS AND STANDARDS
Chapter 19 - Concrete
Section 1910 - MINIMUM SLAB PROVISIONS
Subsection 1910.1 - General
Current through Register 1531, September 27, 2024
The thickness of concrete floor slabs supported directly on the ground shall not be less than 31/2 inches (89 mm). A 6-mil (0.006 inch; 0.15 mm) polyethylene vapor retarder with joints lapped not less than 6 inches (152 mm) shall be placed between the base course or subgrade and the concrete floor slab, or other approved equivalent methods or materials shall be used to retard vapor transmission through the floor slab.
Exception: A vapor retarder is not required:
1. For detached structures accessory to occupancies in Group R-3, such as garages, utility buildings or other unheated facilities.
2. For unheated storage rooms having an area of less than 70 square feet (6.5 m2) and carports attached to occupancies in Group R-3.
3. For buildings of other occupancies where migration of moisture through the slab from below will not be detrimental to the intended occupancy of the building.
4. For driveways, walks, patios and other flatwork which will not be enclosed at a later date.
5. Where approved based on local site conditions.