Code of Massachusetts Regulations
780 CMR - STATE BOARD OF BUILDING REGULATIONS AND STANDARDS
Chapter 1 - Scope and Administration
Part 2 - ADMINISTRATION AND ENFORCEMENT
Section 110 - INSPECTIONS
Subsection 110.6 - Approval required

Universal Citation: 780 CMR MA Code of Regs 110.6
Current through Register 1531, September 27, 2024

Work shall not be done beyond the point indicated in each successive inspection without first obtaining the approval of the building official. The building official, upon notification, shall make the requested inspections and shall either indicate the portion of the construction that is satisfactory as completed, or notify the permit holder or his or her agent wherein the same fails to comply with this code. Any portions that do not comply shall be corrected and such portion shall not be covered or concealed until authorized by the building official.

Disclaimer: These regulations may not be the most recent version. Massachusetts may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.