(1) Project Representative. Where the Department has determined that the services of a project representative are required, the LHA shall advertise for, and select a project representative to monitor daily construction activity. Both the project representative and the project representative's compensation shall require approval of the LHA and the Department.
(2) Contract Officer. The LHA shall designate a contract officer whose function shall be to review payment requisitions from the contractor and to approve periodic payments to the contractor.
(3) Contractor Payments. The LHA shall make payments on the payment requisitions following approval by the contract officer.
(4) Change Orders. The LHA shall consider requests for change orders in accordance with applicable contract provisions, the Department's procedures, and applicable law.
(5) Construction Disputes. Construction disputes between the contractor and designer shall be resolved in the manner specified by the owner-contractor contract and any applicable administrative procedures of the Department.
(6) RCAT Participation. Any LHA participating in the RCAT Program shall involve the RCAT in decisions relating to projects receiving Capital Funds in accordance with 760 CMR 11.00.
(7) CPS Update. Upon completion of a project, the LHA (with the assistance of its RCAT, if applicable) shall update the CPS to reflect the work performed.