Code of Massachusetts Regulations
522 CMR - BOARD OF BOILER RULES
Title 522 CMR 3.00 - Power Reactor Vessels and Piping and Unfired Pressure Vessels As Used In Atomic Energy Installations
Section 3.05 - Inspector and Records

Universal Citation: 522 MA Code of Regs 522.3

Current through Register 1531, September 27, 2024

(1) An Authorized Nuclear Inspector and Authorized Nuclear Inspector (Concrete) shall be on the site during the mechanical construction and testing phases of every nuclear reactor installation, its components, appurtenances, containment vessel, and piping systems. The District Engineering Inspector may make such inspections as deemed appropriate.

(2) The Owner/User shall keep permanent records to maintain complete traceability of all material used in the construction of any nuclear reactor plant. These records shall include certificates of chemical and physical properties.

(a) Permanent records shall be kept at the plant site to maintain complete traceability of all welds that fall within the limits of the 2015 ASME Boiler and Pressure Vessel Code Section III, Rules for Construction of Nuclear Facility Components.

(b) Permanent records shall be maintained identifying all welders, and their qualifications, performing welds covered in 522 CMR 3.05(2)(a).

Disclaimer: These regulations may not be the most recent version. Massachusetts may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.