(1) An Authorized Nuclear Inspector and Authorized Nuclear Inspector (Concrete) shall be on the site during the mechanical construction and testing phases of every nuclear reactor installation, its components, appurtenances, containment vessel, and piping systems. The District Engineering Inspector may make such inspections as deemed appropriate.
(2) The Owner/User shall keep permanent records to maintain complete traceability of all material used in the construction of any nuclear reactor plant. These records shall include certificates of chemical and physical properties.
(a) Permanent records shall be kept at the
plant site to maintain complete traceability of all welds that fall within the
limits of the 2015 ASME Boiler and Pressure Vessel Code
Section III, Rules for Construction of Nuclear Facility
Components.
(b) Permanent
records shall be maintained identifying all welders, and their qualifications,
performing welds covered in
522
CMR 3.05(2)(a).
Disclaimer: These regulations may not be the most recent version. Massachusetts may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.