Code of Massachusetts Regulations
522 CMR - BOARD OF BOILER RULES
Title 522 CMR 2.00 - Power Boilers
Section 2.03 - Construction
Current through Register 1531, September 27, 2024
(1) Heat Recovery Steam Generators (HRSGs). All heat recovery steam generators built after May 1, 2000, shall be built to the ASME Boiler and Pressure Vessel Code Section I, Rules for Construction of Power Boilers adopted at the time of installation.
(2) Restrictions, Dual Pressure Controls, Bypass Switches.
(3) Remote Monitoring Systems. When remote monitoring systems on Steam Boilers are in use, they shall monitor, but not be limited to: steam pressure, and water level, and include a remote shut down switch. All remote monitoring systems must be installed with uninterruptible system signals and include visible alarms and annunciators.