Title 400 CMR 3.00 - Expedited State Permitting
Section 3.09 - Permit Application Modifications
Current through Register 1531, September 27, 2024
(1) Where an applicant seeks to modify a permit application after the permit review period has commenced under 400 CMR 3.07, the filing of the permit application modification shall toll the permit review period. Issuing authorities shall make every reasonable effort to review modification requests within as short a period as is feasible to maintain the integrity of the Program. An issuing authority shall notify the applicant in writing by mail or electronic mail within 20 business days of receipt of a request for a modification whether the modified application can be reviewed within the time remaining in the permit review period, cannot be reviewed within the time remaining in the permit review period, or needs additional information for the issuing authority to render a decision.
(2) If an issuing authority determines during the 20 business days it has to review the modification request that the permit will be denied as a result of the proposed modification, the issuing authority shall notify the applicant and the applicant may: