Code of Massachusetts Regulations
400 CMR - EXECUTIVE OFFICE OF ECONOMIC DEVELOPMENT
Title 400 CMR 2.00 - Expedited Permitting
Section 2.16 - State Permitting
Reviews required under the Massachusetts Environmental Policy Act, M.G.L. c. 30, §§ 61 through 62H, or the Massachusetts Historical Commission, M.G.L. c. 9, §§ 26 through 27C shall conclude within 120 calendar days of a state determination of completeness of required review materials, as established by the executive office of environmental affairs in consultation with the state secretary. The aforementioned reviews shall take place concurrently with the 180-calendar-day municipal permitting review process. The secretary of environmental affairs and the state secretary shall establish time frames for all required filings and additional filings by the applicant in order to comply with 400 CMR 2.16. In the event an applicant fails to comply with all relevant time frames, the time shall be tolled until the applicant files the required documents.