Code of Massachusetts Regulations
310 CMR - DEPARTMENT OF ENVIRONMENTAL PROTECTION
Title 310 CMR 40.0000 - Massachusetts Contingency Plan
Subpart K - AUDITS
Section 40.1170 - Post-audit Completion Statements

Current through Register 1537, December 20, 2024

(1) Upon completion of the activities required by the Department in a Notice of Audit Findings or any approved Audit Follow-up Plan, the RP, PRP or Other Person undertaking such activities shall submit a Post-audit Completion Statement to the Department using a form established by the Department for such purpose.

(2) Each Post-Audit Completion Statement shall include the following information:

(a) an LSP Opinion as to whether the response actions required by the Notice of Audit Findings and any approved Audit Follow-up Plan have been completed in accordance with M.G.L. c. 21E, 310 CMR 40.0000, the terms of any Department approval, and any other applicable laws and requirements;

(b) a description of the response actions completed pursuant to the Notice of Audit Findings and any approved Audit Follow-up Plan;

(c) the investigatory and monitoring data obtained, if any, during the implementation of such response actions;

(d) any other information required by the Department in the Notice of Audit Findings or any approved Audit Follow-up Plan; and

(e) a description of additional response activities, if any, necessary to confirm, demonstrate or achieve compliance with the requirements stated in the Notice of Audit Findings or any approved Audit Follow-up Plan.

Disclaimer: These regulations may not be the most recent version. Massachusetts may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.