(1) For a disposal site where Active Operation and Maintenance of a remedial action is conducted prior to the submittal of a Final Inspection Report and Phase IV Completion Statement to test and monitor the initial implementation and operation of the Comprehensive Remedial Alternative, a Remedial Monitoring Report shall be submitted to the Department on a form established by the Department for such purposes at the following frequency:
(2) For a disposal site where Active Operation and Maintenance of the selected Comprehensive Remedial Alternative is conducted prior to the submittal of a Final Inspection Report and Phase IV Completion Statement to test and monitor the initial implementation and operation of the Comprehensive Remedial Alternative, a Phase IV Status Report, as described in 310 CMR 40.0877(4) shall be submitted with the initial Remedial Monitoring Report and every six months thereafter.
(3) Unless otherwise specified by the Department, for a disposal site where Active Operation and Maintenance of the selected Comprehensive Remedial Alternative is not conducted prior to the submittal of a Final Inspection Report and Phase IV Completion Statement, a Phase IV Status Report shall not be required, but may be submitted at the discretion of the person(s) conducting response actions.
(4) A Phase IV Status Report shall include, as appropriate, the following:
(5) After the submittal of a Phase IV Completion Statement, the person(s) conducting the Comprehensive Remedial Action shall submit Status and Remedial Monitoring Reports for the continued Active Operation and Maintenance of a remedial action initiated during Phase IV pursuant to the requirements of 310 CMR 40.0892 or 40.0897 and 40.0898, as applicable.