(1) The following outcomes are possible upon completion of a Phase II Comprehensive Site Assessment:
(a) Comprehensive Remedial Actions
are necessary at the site to achieve a Permanent or Temporary Solution as
described in
310
CMR 40.1000. A Phase III study for the
identification, evaluation and selection of Comprehensive Remedial Action
Alternatives as described in
310
CMR 40.0850 is necessary to select a remedial
action alternative; or
(b) the
requirements of a Permanent Solution under
310
CMR 40.1000 have been met, and a Permanent
Solution Statement supported by information provided in the Phase II report
shall be submitted to the Department.
Disclaimer: These regulations may not be the most recent version. Massachusetts may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.