(1) Initial Site Investigation Activities.
(a) Initial Site
Investigation Activities shall consist of limited investigative and assessment
actions of sufficient scope and level of effort to make and/or guide
determinations on required and appropriate response actions at a site. Initial
Site Investigation Activities may include, without limitation:
1. evaluation of records relating to the
release, threat of release or impacted site;
2. evaluation of underground storage tank
testing results;
3. testing and/or
retesting of underground storage tanks;
4. evaluation of environmental monitoring
data;
5. limited sampling and
analysis of soil, sediment, groundwater, surface water, soil gas, indoor air or
ambient air; and
6. any other
limited investigations, monitoring, surveys, testing or information gathering
activities necessary to evaluate releases and threats of release of oil and/or
hazardous material, excluding removal and containment actions.
(b) The objective of Initial Site
Investigation Activities is to obtain preliminary information and data on a
release, a threat of release and/or site in order to:
1. determine the existence, source, nature
and approximate extent of the release or threat of release;
2. determine if the release or threat of
release poses or could pose an Imminent Hazard, as described in
310
CMR 40.0321;
3. determine if an Immediate Response Action
is necessary, as described in
310
CMR 40.0412;
4. determine if a Limited Removal Action is
appropriate at the site, as described in
310
CMR 40.0318;
5. determine if a Release Abatement Measure
is appropriate at the site, as described in
310
CMR 40.0440;
6. identify persons who are responsible or
potentially responsible for the release or threat of release;
7. obtain, assemble and record information
and data needed to evaluate the release or threat of release; and
8. determine if a demonstration can readily
be made that a condition of No Significant Risk exists or has been achieved at
the site, before or after the completion of a Limited Removal Action, Immediate
Response Action, or Release Abatement Measure.
(c) The results of Initial Site Investigation
Activities shall:
1. be used to support a
Permanent Solution Statement at the conclusion of Preliminary Response Actions;
or
2. be used as the basis for a
Phase I Report, as described in
310
CMR 40.0480, whenever a Permanent Solution
Statement is not filed for a site within one year of the initial notification
to the Department of a release or threat of release at the site by any person
listed at
310
CMR 40.0331.
(d) When used to support a Permanent Solution
Statement, the results of Initial Site Investigation Activities shall be
reported in a response action report or in a Phase I Report, pursuant to
310
CMR 40.0481, and shall contain all
information, data, records and documents necessary for that purpose.
(e) Assessment activities conducted at a site
prior to Tier Classification, as described in
310
CMR 40.0500, shall not require approval from
the Department.
(2) Immediate Response Actions
(a) Immediate Response Actions are assessment
and/or remedial actions that shall be undertaken in an expeditious manner to
address sudden releases, Imminent Hazards and other time-critical release or
site conditions. Immediate Response Actions shall be taken whenever and
wherever timely actions are required to assess, eliminate, abate or mitigate
adverse or unacceptable release, threat of release and/or site conditions, as
set forth in
310
CMR 40.0412.
(b) Except as provided in
310
CMR 40.0420(12), remedial
actions conducted as part of an Immediate Response Action require prior
approval from the Department.
(3) Release Abatement Measures. Release Abatement Measures are remedial actions that may be voluntarily undertaken by persons conducting response actions at disposal sites. The purposes of Release Abatement Measures are to remediate limited or localized releases, and/or to mitigate the impacts of larger releases until such time as more comprehensive remedial actions can be instituted at the disposal site, in accordance with 310 CMR 40.0800.
Disclaimer: These regulations may not be the most recent version. Massachusetts may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.