Section 19.107 - Construction Certification
Current through Register 1531, September 27, 2024
(1) The construction of a permitted landfill shall be accomplished in compliance with a quality assurance/quality control (QA/QC) plan approved by the Department.
(2) The owner or operator shall hire an independent professional Massachusetts registered engineer, knowledgeable and experienced in matters of landfill construction who shall oversee all construction activities. The engineer shall:
(3) Liners and final covers shall be constructed under the direction of a person with extensive experience in the installation of liners and final caps. Each phase of construction of a liner or cap shall be carried out and inspected under the direction of the independent professional engineer who shall certify that each phase of construction was completed in accordance with approved plans and specifications.
(4) The owner or operator shall submit a copy of the engineer's certification, as required at 310 CMR 19.011 on all construction and QA/QC activities to the Department.