Code of Massachusetts Regulations
301 CMR - EXECUTIVE OFFICE OF ENERGY AND ENVIRONMENTAL AFFAIRS
Title 301 CMR 25.00 - Designation Of Port Areas
Section 25.04 - Designation Standards
Current through Register 1531, September 27, 2024
(1) Designation of Waters. An area of water reviewed under 301 CMR 25.00 shall be included or remain in a DPA if and only if CZM finds that the area is in substantial conformance with the following criteria governing suitability to accommodate water-dependent industrial use, as appropriate to the harbor in question:
(2) Designation of Lands. An area of land reviewed under 301 CMR 25.00 shall be included or remain in a DPA if and only if CZM finds that the area is in substantial conformance with the following criteria governing suitability to accommodate Water-dependent Industrial Use, as appropriate to the harbor in question:
(3) Commentary. As a general rule, CZM intends to apply the foregoing suitability criteria in the context of groups of parcels that form coherent planning units, rather than to individual project sites or other properties under common ownership or control. DPA-related attributes typically vary across different parcels, such that the combined characteristics of associated parcels in the same general vicinity are not reflected accurately in the characteristics of any single property. For this reason, it is important that geographic areas subject to review be sized and configured in a manner that allows consideration of all relevant factors affecting overall suitability to accommodate Water-dependent Industrial Use.