Section 11.11 - Waivers
Current through Register 1531, September 27, 2024
(1) Standards for all Waivers. The Secretary may waive any provision or requirement in 301 CMR 11.00 not specifically required by MEPA and may impose appropriate and relevant conditions or restrictions, provided that the Secretary finds that strict compliance with the provision or requirement would:
(2) Presumptions to be Rebutted for EIR Waiver. The mandatory EIR review thresholds identify Projects or aspects thereof that are presumed to have particularly significant environmental impacts, and for which an EIR is presumed to benefit the Project and the environment. Consequently, a waiver of an EIR review threshold shall follow the review of an ENF and shall be based on a rebuttal of these presumptions.
(3) Determinations for EIR Waiver. In the case of a waiver of a mandatory EIR review threshold, the Secretary shall at a minimum base the finding required in accordance with 301 CMR 11.11(1)(b) on a determination that:
(4) Determinations for Phase One Waiver. In the case of a partial waiver of a mandatory EIR review threshold that will allow the Proponent to proceed with phase one of the Project prior to preparing an EIR, the Secretary shall base the finding required in accordance with 301 CMR 11.11(1)(b) on a determination that:
(5) Request for Waiver. A Proponent shall request a waiver in writing and shall address with particularity any findings that the Secretary is required to make in accordance with 301 CMR 11.11(1) through (4). The Proponent who requests a waiver shall be deemed to consent to an extension of the review period in accordance with 301 CMR 11.05(8). The Secretary shall publish notice of this request in the next Environmental Monitor in accordance with 301 CMR 11.15(2).
(6) Secretary's Decision on Waiver. If the Secretary decides that a waiver request has merit, the Secretary shall prepare a record of decision that describes the Project, the nature and extent of MEPA jurisdiction, and the potential environmental impacts from the Project and mitigation measures, and sets forth the reasons for the waiver, including any findings required in accordance with 301 CMR 11.11(1) through (4). The Secretary shall issue a draft record of decision for each waiver or partial waiver of an EIR review threshold and publish the draft record of decision in the next Environmental Monitor in accordance with 301 CMR 11.15(2), which begins the public comment period. The public comment period lasts for 14 Days, unless extended by the Secretary with the consent of the Proponent. An extension shall not ordinarily exceed 14 Days. During the public comment period, the Secretary shall receive written comments into the record from any Agency or Person concerning the draft record of decision. The Secretary shall issue a final record of decision or a Scope within seven Days after the close of the public comment period. The Secretary shall publish notice of each decision on a waiver request in the next Environmental Monitor in accordance with 301 CMR 11.15(2).