Section 11.08 - EIR Review and Decision
Current through Register 1531, September 27, 2024
(1) Publication and Review Period. Upon receiving the EIR, the Secretary shall publish notice of the availability of the EIR in the next Environmental Monitor in accordance with 301 CMR 11.15(2), which begins the EIR review period. The EIR review period lasts for 37 Days, unless extended by the Secretary on account of the Proponent's failure to meet circulation or Public Notice requirements, with the consent of the Proponent for a draft EIR or as part of a Special Review Procedure.
(2) Investigation. After receiving the EIR, the Secretary shall review the EIR and may review any relevant information from any other source to determine whether the EIR is adequate.
(3) Informal and Informational Public Consultation. An Agency undertaking a Project may hold public hearings, informal workshops, or public meetings at appropriate times prior to and during preparation of an EIR. The Agency shall provide at least seven Days notice of any hearing, workshop, or meeting to allow any other Agency or Person to prepare adequately and to make informed comments at the hearing, workshop, or meeting. The Secretary may hold an informational meeting prior to or during review of the EIR, and may, in the Scope, require the Proponent to hold an informational meeting.
(4) Public Comment Period, Extensions, Late Comments. After receiving the EIR, the Secretary shall receive into the record written comments from any Agency or Person, concerning the Project, its alternatives, its potential environmental impacts, mitigation measures and the adequacy of the EIR, provided that the subject matter of the comment is within the Scope. Comments on the EIR shall be filed with the Secretary within 30 Days of the publication of the notice of the availability of the EIR in the Environmental Monitor, unless the public comment period is extended by the Secretary on account of the Proponent's failure to meet circulation or Public Notice requirements, with the consent of the Proponent for a draft EIR or as a part of a Special Review Procedure. An extension shall not ordinarily exceed 30 Days. The Secretary may accept a late comment, provided that it is received prior to the Secretary's decision on the EIR.
(5) Withdrawal and Refiling of Single or Final EIR. With the consent of the Secretary, the Proponent may withdraw a single or final EIR prior to the Secretary's decision on the single or final EIR to provide further opportunity for public review. After such withdrawal, the Proponent may refile the single or final EIR, with or without changes, additions, or deletions, which shall be clearly identified in the refiled single or final EIR. The Secretary shall publish notice of the availability of the refiled single or final EIR in the next Environmental Monitor in accordance with 301 CMR 11.15(2). A refiled single or final EIR restarts the EIR review period in accordance with 301 CMR 11.08(1) and the public comment period in accordance with 301 CMR 11.08(4) and the legal challenge periods in accordance with 301 CMR 11.14.
(6) Comments Outside Scope. The Secretary may accept a comment not within the Scope provided that the Secretary finds that it is material and that it was not reasonably possible with due diligence to have made it during review of the previous review document or that the comment raises critically important issues regarding the potential environmental impacts of the Project.
(7) Agency Review. An Agency shall review an EIR circulated to it by the Proponent. If it appears that the Project requires Agency Action by the Agency or may significantly affect any interest of the Agency or any statutes or regulations administered by the Agency, the Agency shall:
A Participating Agency's failure to specify an aspect of the Project or issue requiring additional description or analysis shall have the effect of a determination that the information presented in the EIR and any previous review document, together with information already provided in any application for a Permit, Financial Assistance or a Land Transfer, sufficiently defines the nature and general elements (but not necessarily the technical details) of the Agency Action on the Project, such that the Participating Agency can fulfill its obligations in accordance with M.G.L. c. 30, §§ 61 and 62K, and 301 CMR 11.12(5).
(8) Secretary's Determination on EIR.
(9) Notification to Department of Environmental Protection for Projects Located in Landlocked Tidelands. If the Project is located in landlocked tidelands as defined in 310 CMR 9.02, then within 30 days after a certificate is issued determining that a final EIR or a single EIR is adequate the Proponent shall file with the Department of Environmental Protection a completed form notifying the Department of Environmental Protection that work will be conducted within landlocked tidelands. The Proponent shall attach the certificate to the form. The Proponent shall comply with all obligations set forth in the certificate and the Department of Environmental Protection shall enforce such conditions consistent with M.G.L. c. 30 § 62I.
(10) Notification of Commencement of Construction. The Proponent shall notify the Secretary upon Commencement of Construction for any Project for which the Secretary required an EIR.