Title 220 CMR 151.00 - Rail Fixed Guideway System: System Safety Program Standard
Section 151.12 - Track Maintenance
Current through Register 1537, December 20, 2024
(1) Unless otherwise structurally supported, all track must be supported by ballast material which will:
(2) Crossties shall be made of a material to which rail can be securely fastened.
(3) Each 39-foot segment of track shall have the minimum number and type of crossties as indicated in the following table:
MAXIMUM TRACK SPEED |
MINIMUM NUMBER OF TIES |
|
Tangent Track* |
Curved Track** |
|
15 miles per hour |
5 |
6 |
25 miles per hour |
8 |
9 |
60 miles per hour |
8 |
10 |
* Track that is straight or has a radius curve greater than 1000 feet. ** Track having a radius curve measuring less than 1000 feet. |
Crossties required shall be of the type which are not:
(4) Gage is measured between the heads of the rails at right-angles to the rails in a plane e of an inch below the top of the rail head.
(5) Gage must be within the limits prescribed in the following table:
MAXIMUM TRACK SPEED |
MINIMUM TRACK GAGE |
MAXIMUM TRACK GAGE |
10 miles per hour |
56" |
58" |
60 miles per hour |
56" |
573/4" |
(6) Each rail joint, insulated joint, and compromise joint must be of the proper design and dimensions for the rail on which it is applied.
(7) If a joint bar is cracked, broken, or because of wear allows excessive vertical movement of either rail when all the bolts are tight, it must be replaced.
(8) If a joint bar is cracked or broken between the middle two bolt holes it must be replaced.
(9) In the case of conventional jointed rail in passenger-service track, each rail must be bolted with at least two bolts at each joint. Yard and storage track joints must be bolted with at least one bolt on each rail.
(10) In the case of continuous welded rail (CWR) track, each rail must be bolted with at least two bolts at each joint used to connect CWR strings or to connect CWR to conventional rail.
(11) Each joint bar must be held in position by track bolts tightened to allow the joint bar to firmly support the abutting rail ends and to allow longitudinal movement of the rail in the joint to accommodate expansion and contraction due to temperature variations.
(12) When any condition in 220 CMR 151.12(9) and (10) is not satisfied, an operating restriction must be put in place immediately until the condition is satisfied. The Transportation Authority shall notify the Program Manager of the imposition or removal of an operating restriction within 48 hours of said action.