Current through Register 1531, September 27, 2024
(1)
General.
(a) Cables
operating above 600 volts to ground shall have a continuous shield, sheath or
concentric neutral which is effectively grounded.
(b) Cables of the same circuit operating
below 600 volts to ground and without an effectively grounded shield or sheath
shall be placed in close proximity (no intentional separation) to each
other.
(c) Communications cables
containing special circuits supplying power solely to communications equipment
shall comply with the requirements of
220 CMR 126.34(5)(a)
through
126.34(5)(e).
(2) Location and Routing.
(a)
General.
1. Cables should be located so as to be
subject to the least disturbance practical. Cables to be installed parallel to
other subsurface structures should not be located directly over or under other
subsurface structures, but if this is not practical, the rules on clearances in
220 CMR 126.35(3) should be followed.
2. Cables should be installed in as straight
and direct a line as practical. Where bends are required, the minimum radius
shall be sufficiently large to prevent damage to the cable being
installed.
3. Cable systems should
be routed so as to allow safe access for construction, inspection and
maintenance.
4. The location of
structures in the path of the projected cable route shall, as far as practical,
be determined prior to the trenching, plowing or boring operation.
(b)
Natural
Hazards. Routes through unstable soil such as mud, shifting soils,
corrosive soils or other natural hazards, should be avoided. If burying is
required through areas with natural hazards, the cables shall be constructed
and installed in such a manner as to protect them from damage. Such protective
measures should be compatible with other installations in the area.
(c)
Other
Conditions.
1.
Swimming Pools. Supply cable shall not be installed
within five feet of a swimming pool or its auxiliary equipment.
2.
Buildings and Other
Structures. Cable should not be installed directly under building
or storage tank foundations. Where a cable must be installed under such a
structure, the structure shall be suitably supported to prevent transfer of a
harmful load onto the cable.
3.
Railroad Tracks. The installation of cable
longitudinally under the ballast section for railroad tracks should be avoided.
Where cable must be installed longitudinally under the ballast section of a
railroad, it should be located at a depth of not less than 60 inches below the
top, of the rail.
Where a cable crosses under railroad tracks, the same
clearances indicated in
220 CMR 126.32(1)(e)
shall apply.
4.
Highways and
Streets. The installation of cable longitudinally under traveled
surfaces of highways and streets should be avoided. When cable must be
installed longitudinally under the roadway, it should be installed in the
shoulder or within the limits of one lane of traffic if practical.
5.
Submarine
Crossings. Submarine crossings should be routed and/or installed
so they will be protected from erosion by tidal action or currents. They should
not be located where ships normally anchor.
(3)
Clearance from Other
Underground Structures (sewers, water lines, fuel lines, building
foundations, steam lines, other supply or communication conductors not in
random separation, etc.).
(a)
Horizontal Clearance. The horizontal clearance between
direct buried cable and other underground structures should be controlled at a
minimum of 12 inches or larger as necessary to permit access to and maintenance
of either facility without damage to the other. Installations with less than 12
inches horizontal separation shall conform with the requirements of 220 CMR
126.35(3)(c) and/or 126.35(5).
(b)
Crossings.
1. Where
a cable crosses under another underground structure, the structure shall be
suitably supported to prevent transfer of a harmful load onto the cable
system.
2. Where a cable crosses
over another underground structure, the cable shall be suitably supported to
prevent transfer of a harmful load onto the structure.
3. Adequate support may be provided by
installing the facilities with sufficient vertical separation.
4. Adequate vertical clearance shall be
maintained to permit access to and maintenance of either facility without
damage to the other. A vertical clearance of 12 inches is, in general,
considered adequate but the parties involved may agree to a lesser
separation.
(c)
Parallel Facilities. If conditions require a cable
system to be installed with less than 12 inches horizontal separation or
directly over and parallel to another underground structure (or another
underground structure installed directly over and parallel to a cable), it may
be done providing all parties are in agreement as to the method. Vertical
clearance shall be at least 12 inches except where the parties mutually agree
that lesser separation will be adequate.
(d) Thermal Protection. Cable should be
installed with sufficient clearance from other underground structures, such as
steam or cryogenic lines, to avoid thermal damage to the cable. Where it is not
practical to provide adequate clearance, a suitable thermal barrier shall be
placed between the two facilities.
(4)
Installation.
(a)
Trenching. The
bottom of the trench receiving direct buried cable should be relatively smooth,
undisturbed earth, well-tamped earth or sand. When excavation is in rock or
rocky soils, the cable shall be laid on a protective layer of well-tamped
backfill. Backfill within four inches of the cable shall be free of materials
that may damage the cable. Backfill should be adequately compacted. Machine
compaction should not be used within four inches of the cable.
(b)
Plowing.
1. Plowing in of cable in soil containing
rock or other solid material should be done in such a manner that the solid
material will not damage the cable, either during the plowing operation or
afterward.
2. The design of cable
plowing equipment and the plowing-in operation should be such that the cable
will not be damaged by bending, side-wall pressure or excessive cable
tension.
(c)
Boring. Where a cable system is to be installed by
boring and the soil and surface loading conditions are such that solid material
in the region may damage the cable, the cable shall be adequately
protected.
(d)
Depth of
Burial. The distance between the top of a cable and the surface
under which it is installed (depth of burial) shall be sufficient to protect
the cable from injury or damage imposed by expected surface usage.
1. Minimum burial depths shall be as
indicated in 220 CMR 126.35(4)(d)1. Table 1:
Table 1
CONDUCTORS OR CABLES
Voltage Phase to
Ground
|
Depth of Burial
(Inches)
|
600 and below
|
24
|
601 to 22,000
|
30
|
22,001 to 40,000
|
36
|
40,001 and above
|
42
|
2. In
areas where frost conditions could damage cables, greater burial depths than
indicated above may be desirable.
3. When lesser depths than indicated above
cannot be avoided, adequate supplemental protection shall be
provided.
4. Where the surface
under which a cable is to be installed is not to designated final grade, the
cable shall be placed so as to meet or exceed the requirements indicated above,
both at the time of installation and subsequent thereto.
(5)
Random Separation
-- Additional Requirements. The following rules apply to
conductors or cables when the radial separation between them will be less than
12 inches.
(a)
Supply Conductors
or Cables. The conductors or cables of a supply circuit and those
of another supply circuit may be buried together at the same depth with no
deliberate separation between facilities, provided all parties involved are in
agreement.
(b)
Communication Conductors or Cables. The conductors or
cables of a communication circuit and those of another communication circuit
may be buried together and at the same depth with no deliberate separation
between facilities, provided all parties involved are in agreement.
(c)
Supply and Communication
Conductors or Cables. Supply cables or conductors and
communication cables or conductors may be buried together at the same depth
with no deliberate separation between facilities, provided all parties involved
are in agreement and the following requirements are met:
1.
Voltage. Grounded
supply systems shall not be operated in excess of 22,000 volts to ground.
Ungrounded supply systems shall not be operated in excess of 5300 volts phase
to phase.
2.
Bare
Grounded Conductor. A supply facility operating above 300 volts to
ground must include a bare grounded conductor in continuous contact with the
earth. This conductor, adequate for the expected magnitude and duration of the
fault current which may be imposed, shall be, one of the following: a sheath
and/or shield; multiple concentric conductors closely spaced circumferentially;
a separate bare conductor in contact with the earth and in close proximity to
the cable where such cable or cables also have a grounded sheath or shield not
necessarily in contact with the earth. The sheath and/or shield as well as the
bare conductor shall be adequate for the expected magnitude and duration of the
fault currents which may be imposed.
Note: This is applicable when cable in
non-metallic duct is considered as a direct buried cable installation and
random separation is desired.
Exception: Where a buried cable passes
through a short section of conduit, such as under a roadway, the contact with
earth of the grounded conductor can be omitted, provided the grounded conductor
is continuous through the conduit. The bare conductor(s) in contact with the
earth shall be of suitable corrosion-resistant material.
3.
Ungrounded Supply
Systems. Cables of an ungrounded supply system operating above 300
volts shall be of effectively grounded concentric shield construction in
continuous contact with the earth. Such cables shall be maintained in close
proximity to each other.
(d)
Multiple Cable
Systems. More than one cable system buried in random separation
may be treated as one system when considering clearance from other underground
structures or facilities.
(e)
Protection.
1.
Supply circuits operating above 300 volts to ground or 600 volts between
conductors shall be so constructed, operated and maintained that when faulted,
they shall be promptly de-energized initially or following subsequent
protective device operation. (Phase-to-ground faults for grounded circuits,
phase-to-phase faults for ungrounded circuits.)
2. Ungrounded supply circuits operating above
300 volts shall be equipped with a ground fault indication system.
3. Communication protective devices shall be
adequate for the voltage and currents expected to be impressed on them in the
event of contact with the supply conductors.
4. Adequate bonding shall be provided between
the effectively grounded supply conductor(s) and the communications cable
shield or sheath. (Preferably at intervals not to exceed 1000 feet.)