(1) Each operator of buried cast-iron pipelines shall develop and implement, in accordance with 220 CMR 113.05, a written, comprehensive program and procedures regarding the replacement and abandonment of cast-iron pipelines. The program and procedures shall include, but not be limited to:
(2) Each operator, to meet the requirements of 220 CMR 113.05(1)(b), shall consider, but not be limited by, the following criteria. In considering these criteria, each operator shall give reasonable regard to incorporating each criterion into the operator's program and procedures required by 220 CMR 113.05(1)(b). If any criterion is not included in the program and procedures, the operator shall make a detailed explanation of the consideration given the excluded criterion and the reason for the exclusion.
(3) Each operator shall establish a written time schedule for replacement or abandonment of cast-iron pipe. The schedule may be updated at any time during each year by the operator and shall include, as practicable, the size, length and location of pipe segments to be replaced or abandoned for each of the next three consecutive calendar years.