Code of Massachusetts Regulations
105 CMR - DEPARTMENT OF PUBLIC HEALTH
Title 105 CMR 120.000 - The Control of Radiation
QUALITY ASSURANCE
Section 120.825 - Technical Analyses

Current through Register 1531, September 27, 2024

(A) The specific technical information shall also include the following analyses needed to demonstrate that the performance objectives set forth in 105 CMR 120.811 through 120.814 will be met:

(1) Pathways analyzed in demonstrating protection of the general population from releases of radioactivity shall include air, soil, groundwater, surface water, plants and animals. The analyses shall clearly identify and differentiate between the roles performed by the natural site characteristics and facility design features in isolating and segregating the wastes. The analyses shall demonstrate that there is assurance that the exposures to humans from the release of radioactivity will not exceed the limits set forth in 105 CMR 120.811.

(2) Analyses of the protection of individuals from inadvertent intrusion shall demonstrate that waste classification and segregation requirements will be met and that intruder barriers will be provided.

(3) Analyses of the protection of individuals during operations shall include assessments or expected exposures due to routine operations and potential accidents during handling, treatment, storage, and disposal of waste. The analyses shall demonstrate that exposures will be controlled to meet the requirements of 105 CMR 120.200.

(4) Analyses of the long term stability of the facility and the need for active long-term maintenance after closure shall be based upon analyses of active natural processes (such as, in the case of a disposal facility, erosion, mass wasting, slope failure, settlement of wastes, infiltration through adjacent soils, and surface drainage of the facility). The analyses shall demonstrate that there will not be a need for long term active maintenance of the facility following closure.

(B) The Operator shall, at any time during licensing, development, operation, closure, post-closure observation and maintenance or institutional control of the facility, immediately notify the Department of any significant change in its technical analysis required to be submitted pursuant to 105 CMR 120.800. Such notification shall include a substitute technical analysis, satisfying the requirements of the Section and demonstrating that the performance objectives set forth in 105 CMR 120.811 through 120.814 will be met by the facility.

Disclaimer: These regulations may not be the most recent version. Massachusetts may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.