A. Interior Cleanup. After completion of the removal, replacement, encapsulation, or reversal involved in an abatement project, the contractor shall:
B. Exterior Cleanup. After completion of the replacement, removal, encapsulation, or reversal involved in an exterior abatement project, the contractor shall:
C. Except as provided in §F, after the cleaning outlined in §§A and B, after a satisfactory inspection under Regulation .12B, every contractor shall repaint with a paint containing not more than 0.06 percent lead in the dried solid, or recoat all surfaces treated, except those encapsulated surfaces which have smooth easily cleanable factory-finished surfaces.
D. Before repainting or recoating under §C, each contractor shall notify the Department that the cleanup required under §§A and B is completed, and shall undergo any inspection required by Regulation .12B.
E. After painting or coating as required under §C, the contractor shall repeat the cleaning process set forth in §A in all interior work areas.
F. After completion of the cleaning required under §E, the contractor shall seal all floors in interior work areas with:
G. In owner-occupied dwellings in which a lead abatement project is being done by the owner and not by a hired contractor, after completion of the replacement, removal, encapsulation, or reversal involved in a lead abatement project, the owner may, instead of following the cleanup procedures set forth in §A:
H. Alternative Procedures. The Department may on a case-by-case basis allow an alternative procedure for cleanup of a lead abatement project, provided that the owner or contractor who uses this procedure shall submit to the Department a written description of the alternative procedure which demonstrates to the satisfaction of the Department that the proposed alternative procedure provides the equivalent degree of dust removal.