Code of Maryland Regulations
Title 21 - STATE PROCUREMENT REGULATIONS
Subtitle 10 - ADMINISTRATIVE AND CIVIL REMEDIES
Chapter 21.10.08 - Prompt Payment of Subcontractors
Section 21.10.08.03 - Responsibilities

Universal Citation: MD Code Reg 21.10.08.03

Current through Register Vol. 51, No. 6, March 22, 2024

A. A contractor who receives a progress payment or a final payment shall pay a subcontractor an undisputed amount to which the subcontractor is entitled within 10 calendar days of receiving the payment.

B. If a contractor withholds payment from a subcontractor within the time period in which the payment normally would be made, the contractor shall:

(1) Notify the subcontractor in writing and state the reason why payment is being withheld;

(2) Provide a copy of the notice to the prime contractor and, if different, to the person or firm that made the progress payment or final payment to the contractor; and

(3) Provide a copy of the notice to the procurement officer.

C. Written Notice of Nonpayment.

(1) If a subcontractor does not receive a payment within the required time period, the subcontractor shall give written notice of the nonpayment to the procurement officer.

(2) The notice shall:
(a) Indicate the:
(i) Name of the contractor and, if different, of the prime contractor;

(ii) Project under which the dispute exists; and

(iii) Amount in dispute;

(b) Provide an itemized description on which the amount is based; and

(c) If known, provide an explanation for any dispute concerning the payment not received.

Disclaimer: These regulations may not be the most recent version. Maryland may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.