Code of Maryland Regulations
Title 21 - STATE PROCUREMENT REGULATIONS
Subtitle 10 - ADMINISTRATIVE AND CIVIL REMEDIES
Chapter 21.10.04 - Contract Claims and Disputes
Section 21.10.04.07 - Contractor's Response to Procurement Agency Claim

Universal Citation: MD Code Reg 21.10.04.07

Current through Register Vol. 51, No. 19, September 20, 2024

A. The contractor shall submit a written response to the procurement agency claim within 30 days of the receipt of the written notice. This period may be extended at the discretion and with the written consent of the procurement officer.

B. The written response shall state:

(1) Whether the contractor denies the procurement agency claim or the relief sought in whole or in part;

(2) The basis of any denial; and

(3) The factual areas of agreement or disagreement.

Disclaimer: These regulations may not be the most recent version. Maryland may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.