Code of Maryland Regulations
Title 21 - STATE PROCUREMENT REGULATIONS
Subtitle 07 - CONTRACT TERMS AND CONDITIONS
Chapter 21.07.02 - Mandatory Construction Contract Clauses
Section 21.07.02.05 - Differing Site Conditions
Current through Register Vol. 51, No. 19, September 20, 2024
Mandatory provision for all construction contracts:
"Differing Site Conditions
(1) subsurface or latent physical conditions at the site differing materially from those indicated in this contract, or
(2) unknown physical conditions at the site of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in this contract. The procurement officer shall promptly investigate the conditions, and if the procurement officer finds that such conditions do materially so differ and cause an increase or decrease in the Contractor's cost of, or the time required for, performance of any part of the work under this contract, whether or not changed as a result of such conditions, an equitable adjustment shall be made and the contract modified in writing accordingly.