Code of Maryland Regulations
Title 21 - STATE PROCUREMENT REGULATIONS
Subtitle 07 - CONTRACT TERMS AND CONDITIONS
Chapter 21.07.01 - Mandatory Contract Provisions - All Contracts (except as provided under COMAR 21.05.07, 21.07.02, and 21.07.03)
Section 21.07.01.13 - Delays and Extensions of Time

Universal Citation: MD Code Reg 21.07.01.13
Current through Register Vol. 51, No. 19, September 20, 2024

Mandatory provision for all contracts. It shall be in substantially the same form as follows:

"Delays and Extensions of Time"

"The Contractor agrees to prosecute the work continuously and diligently and no charges or claims for damages shall be made by it for any delays or hindrances from any cause whatsoever during the progress of any portion of the work specified in this Contract.

"Time extensions will be granted only for excusable delays that arise from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to, acts of God, acts of the public enemy, acts of the State in either its sovereign or contractual capacity, acts of another Contractor in the performance of a contract with the State, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control and without the fault or negligence of either the Contractor or the subcontractors or suppliers."

Disclaimer: These regulations may not be the most recent version. Maryland may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.