Code of Maryland Regulations
Title 21 - STATE PROCUREMENT REGULATIONS
Subtitle 06 - CONTRACT FORMATION AND AWARD
Chapter 21.06.09 - Invoicing, Payment, and Interest on Late Payments
Section 21.06.09.05 - Payment Period

Universal Citation: MD Code Reg 21.06.09.05

Current through Register Vol. 51, No. 6, March 22, 2024

A. Unless payment is deferred, delayed, or set-off under COMAR 21.02.07.03, payment under a procurement contract shall be made within 30 days:

(1) After the day on which the payment becomes due under the procurement contract; or

(2) If later, after the day on which the agency receives a proper invoice.

B. Payment will be considered to be made on the settlement date for an electronic funds transfer payment or the mailing date of the check for a check payment.

C. Payments falling due on a weekend, State holiday, or federal holiday may be made on the following business day without incurring late payment interest penalties.

Disclaimer: These regulations may not be the most recent version. Maryland may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.