Code of Maryland Regulations
Title 21 - STATE PROCUREMENT REGULATIONS
Subtitle 05 - PROCUREMENT METHODS AND PROJECT DELIVERY METHODS
Chapter 21.05.10 - Construction Management at Risk
Section 21.05.10.03 - Selection of the Construction Manager
Universal Citation: MD Code Reg 21.05.10.03
Current through Register Vol. 51, No. 19, September 20, 2024
A. Procurement agencies shall use the competitive sealed proposals procurement method under COMAR 21.05.03 to select the construction manager.
B. Procurement agencies shall obtain separate Board of Public Works approval for preconstruction services, regardless of dollar value, and each GMP that exceeds the Board delegations of procurement and contracting authority in COMAR 21.02.01.04B.
Disclaimer: These regulations may not be the most recent version. Maryland may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.