Code of Maryland Regulations
Title 21 - STATE PROCUREMENT REGULATIONS
Subtitle 05 - PROCUREMENT METHODS AND PROJECT DELIVERY METHODS
Chapter 21.05.10 - Construction Management at Risk
Section 21.05.10.02 - General
Universal Citation: MD Code Reg 21.05.10.02
Current through Register Vol. 51, No. 26, December 27, 2024
A. Procurement agencies not otherwise exempt from this title may not use the construction management at risk project delivery method for construction projects estimated at less than $10,000,000 without prior approval from the Board of Public Works.
B. Cost savings resulting from projects completed below the guaranteed maximum price may be shared between the procurement agency and the construction manager.
Disclaimer: These regulations may not be the most recent version. Maryland may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.