Code of Maryland Regulations
Title 20 - PUBLIC SERVICE COMMISSION
Subtitle 51 - ELECTRICITY SUPPLIERS
Chapter 20.51.03 - Electricity Supplier License Requirements
Section 20.51.03.01 - Licensee's Updated Information

Universal Citation: MD Code Reg 20.51.03.01

Current through Register Vol. 51, No. 6, March 22, 2024

A. In this chapter, a material change means one or more of the following conditions:

(1) PJM Interconnection, LLC has reduced the licensee's unsecured credit allowance to a level below $2,000,000.

(2) The licensee is denied credit by a Maryland electric company.

(3) At least two of the nationally recognized statistical rating organizations have reduced the licensee's rating by two or more grades, or to a level below investment grade.

(4) The licensee has filed for bankruptcy protection or been subjected to involuntary bankruptcy proceedings.

(5) The licensee has had a license revoked, suspended, or restricted in another state.

(6) A parent corporation or other person who has undertaken to guarantee the licensee's financial integrity withdraws the guarantee.

(7) In addition to any of the conditions under §A(1)-(6) of this regulation, if a supplier provides supplier-consolidated billing, a material change includes:
(a) The transfer of supplier-consolidated billing services from a supplier to a third-party agent;

(b) The transfer of supplier-consolidated billing services from one third-party agent to another third-party agent; or

(c) Cancellation of the bonding or collateral for supplier-consolidated billing required under COMAR 20.51.02.08G.

B. Within 10 business days of a material change, a licensed electricity supplier shall:

(1) Update or supplement the information required in the application under COMAR 20.51.02.02B(1), (4), and (5) and COMAR 20.51.02.02E; and

(2) File a copy of the updated or supplemental information with the Commission.

C. Except for information pertaining to the financial integrity of the licensee, a licensee shall provide to the Commission annual updates of the information required in the application under COMAR 20.51.02. The annual update required by this section shall be filed within 120 days of the close of the fiscal year of the licensee.

D. A licensed electricity supplier shall provide additional information as may be required by the Commission.

Disclaimer: These regulations may not be the most recent version. Maryland may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.