Code of Maryland Regulations
Title 09 - MARYLAND DEPARTMENT OF LABOR
Subtitle 12 - DIVISION OF LABOR AND INDUSTRY
Chapter 09.12.81 - Elevator, Escalator, and Chairlift Safety
Section 09.12.81.04 - Final Acceptance Inspection

Universal Citation: MD Code Reg 09.12.81.04

Current through Register Vol. 51, No. 6, March 22, 2024

A. A final acceptance inspection by the Commissioner is required before the Commissioner may issue a certificate of registration and inspection on all new or modified elevator units.

B. A contractor shall request a final acceptance inspection at least 30 days before the date the contractor requests for the final acceptance inspection to be conducted.

C. A contractor may cancel a scheduled inspection under this regulation by written notice to the Commissioner at least 24 hours before the scheduled inspection.

Disclaimer: These regulations may not be the most recent version. Maryland may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.