09.12.81.04. Final Acceptance Inspection

A. A final acceptance inspection by the Commissioner is required before the Commissioner may issue a certificate of registration and inspection on all new or modified elevator units.

B. A contractor shall request a final acceptance inspection at least 30 days before the date the contractor requests for the final acceptance inspection to be conducted.

C. A contractor may cancel a scheduled inspection under this regulation by written notice to the Commissioner at least 24 hours before the scheduled inspection.

(Regulations .04 adopted as an emergency provision effective July 5, 2001 (28:15 Md. R. 1394); adopted permanently effective October 1, 2001 (28:19 Md. R. 1684)
Regulation .04A amended as an emergency provision effective October 15, 2007 (34:23 Md. R. 2019); amended permanently effective February 25, 2008 (35:4 Md. R. 514))
Disclaimer: These regulations may not be the most recent version. Maryland may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.