Code of Maryland Regulations
Title 09 - MARYLAND DEPARTMENT OF LABOR
Subtitle 12 - DIVISION OF LABOR AND INDUSTRY
Chapter 09.12.26 - Crane Safety
Section 09.12.26.11 - Tower Cranes
Current through Register Vol. 51, No. 19, September 20, 2024
A. An employer shall ensure that prior to the erection or modification of any tower crane or supporting structure, a qualified person shall determine the appropriate and safe method to integrate, assemble, and erect the tower crane for that site.
B. The employer shall ensure that when a tower crane is erected, dismantled, jumped, or reconfigured the following are maintained at the site where the work is performed:
C. Except when approved and documented by a qualified person, prior to the commencement of work on the tower crane, the employer shall establish procedures for the particular site for the erection, dismantling, jumping, or reconfiguration work.
D. An employer shall ensure that rigging operations during the erection, dismantling, jumping, or reconfiguring of a tower crane is performed under the direct supervision of a master/lead rigger.
E. An employer shall ensure that a daily job safety briefing is conducted before the commencement of work with all persons working on or around the crane in the following circumstances:
F. An employer shall ensure that the master/lead rigger discuss the following at the daily job safety briefing:
G. An employer shall ensure that erection, dismantling, and inspections shall be conducted in accordance with Chapters 3-1 and 3-2 of the ASME B30.3-2004 Safety Standard for Cableways, Cranes, Derricks, Hoists, Hooks, Jacks, and Slings -Construction Tower Cranes.