Code of Maryland Regulations
Title 09 - MARYLAND DEPARTMENT OF LABOR
Subtitle 12 - DIVISION OF LABOR AND INDUSTRY
Chapter 09.12.01 - Board of Boiler Rules
Section 09.12.01.17 - Installation
Universal Citation: MD Code Reg 09.12.01.17
Current through Register Vol. 51, No. 19, September 20, 2024
A. A new or used boiler, pressure vessel, or piping installation or reinstallation shall be installed in accordance with this chapter.
B. Notice of Installation.
(1) At least 30 days before installing or
reinstalling a boiler or pressure vessel, the installer shall file with the
chief boiler inspector written notice of the installation.
(2) To obtain a waiver, the installer shall
file a written waiver request with the chief boiler inspector:
(a) Installer's name, company name, contact
person, address, telephone number, fax number, and email address;
(b) Owner's name, company name, contact
person, street address, telephone numbers, fax number, and email
address;
(c) User's name, company
name, contact person, street address, telephone numbers, fax number, and email
address;
(d) Name of the location
where the boiler or pressure vessel is installed, company name, contact person,
street address, telephone numbers, fax number, and email address;
(e) Type and use of boiler or pressure
vessel;
(f) If a boiler, the type
of fuel;
(g) If a pressure vessel,
the pressurized fluid;
(h) The
minimum required safety valve capacity;
(i) If the boiler or pressure vessel is
greater than 30 boiler horsepower input or 1,000,000 Btu/hr minimum required
safety valve capacity, and operates at greater than 15 psig, the name and
Maryland license number of the stationary engineer responsible for the boiler
or pressure vessel;
(j)
Manufacturer, date of manufacture, National Board number, and manufacturer's
serial number;
(k) Construction
code and section and stamp;
(I)
Name and contact information of the authorized inspection agency for the
installation;
(m) Planned date of
installation, and planned date of startup; and
(n) Whether a waiver of the 30 day notice
requirement under subsection c of this section is requested, with a detailed
explanation.
C. Waiver of 30-day Notice Requirement.
(1) If emergency or
unusual circumstances are established by the installer, the chief boiler
inspector shall waive the 30-day notice requirement.
(2) To obtain a waiver, the installer shall
file a written waiver request with the Chief Boiler Inspector as soon as the
emergency or unusual circumstances arise; and give a detailed explanation of
the emergency or unusual circumstances.
(3) If
the Chief Boiler Inspector grants a waiver under this section, the Chief Boiler
Inspector shall also advise the installer of when the notice is
due.
D. Except for an existing boiler or pressure vessel being reinstalled, or as otherwise provided by this regulation, a boiler or pressure vessel may not be installed unless:
(1)The boiler or pressure vessel has been
constructed, inspected and stamped in accordance with the ASME Code and
registered with the National Board;
(2) The boiler or pressure vessel has been:
(a) Constructed, inspected and stamped in
accordance with the ASME Code;
(b)
Inspected and the inspector recommends acceptance; and
(c) The Chief Boiler Inspector accepts the
inspector's recommendation; or
(3) The boiler or pressure vessel has been
constructed equal to or greater than Maryland standards and:
(a) The person intending to construct or
install the boiler or pressure vessel:
(i)
Applies to the Chief Boiler Inspector for approval prior to installation;
and
(ii) Together with the
application files the manufacturer's data report covering construction of the
boiler or pressure vessel;
(b) An inspector inspects the boiler or
pressure vessel during construction and approves the design, materials,
fabrication, welding, welding specification, welder's qualifications, processes
and workmanship; and
(c) The Chief
Boiler Inspector approves the boiler or pressure vessel and its
installation.
E. Reinstallation
(1) A used boiler or pressure vessel not
moved to another state for use, or repair, or alteration may be reinstalled if
the:
(a) Owner applies to the Chief Boiler
Inspector for permission;
(b) Owner
submits documents required by the Chief Boiler Inspector; and
(c) Chief Boiler Inspector approves the
reinstallation.
(2) A
used standard boiler or pressure vessel, if moved outside the state for use,
repair, or alteration, may be reinstalled if the:
(a) Owner applies to the Chief Boiler
Inspector for permission;
(b) Owner
submits documents required by the Chief Boiler Inspector; and
(c) Chief Boiler Inspector approves the
reinstallation.
(3) A
used nonstandard boiler or pressure vessel, if moved outside the State for use,
repair or alteration, may be reinstalled in Maryland if the:
(a) Owner applies to the Chief Boiler
Inspector and the Board for permission;
(b) Owner submits documents required by the
Chief Boiler Inspector and the Board; and
(c) The Board of Boiler Rules approves the
reinstallation.
(4)
Fittings and appliances of a stationary boiler or pressure vessel which is
moved and reinstalled shall comply with the requirements for new
installations.
Disclaimer: These regulations may not be the most recent version. Maryland may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.