Section 09.12.01.07 - Gas-Fired Installations

Universal Citation: MD Code Reg 09.12.01.07

Current through Register Vol. 50, No. 25, December 15, 2023

A. A burner in a gas-fired installation shall be tested and certified by the American Gas Association.

B. A gas-fired boiler shall have a vent or flue that terminates at an acceptable location outside the building.

C. The size of the vent or flue shall be:

(1) That recommended by the boiler manufacturer;

(2) At least 4 inches in diameter or equivalent area; and

(3) If the horizontal run exceeds 10 feet, at least 6 inches in diameter or equivalent area.

Regulations .07 adopted effective November 4, 1985 (12:22 Md. R. 2103)
Regulations .07 adopted effective June 1, 1989 (16:10 Md. R. 1106)

Disclaimer: These regulations may not be the most recent version. Maryland may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.