Code of Maine Rules
16 - DEPARTMENT OF PUBLIC SAFETY
642 - BUREAU OF BUILDING CODES AND STANDARDS
Chapter 2 - MAINE UNIFORM BUILDING CODE AND UNIFORM ENERGY CODE - THIRD PARTY INSPECTORS ("TPI")
Section 642-2-6 - INSPECTION REPORT

Current through 2024-13, March 27, 2024

1. The Inspection Report shall be prepared by the TPI, and shall include, but not be limited to the following information.

A. The Inspection Report shall contain a clear and concise description of each Code item reviewed for compliance.

B. The Inspection Report shall provide instruction and guidance to the Applicant to identify and resolve items found to be in noncompliance with the Code.

C. Inspection items found to be in noncompliance shall be described and identified by Code section.

D. Correction of non-conforming inspection items shall be documented.

E. All change orders that significantly modify the planned construction, shall be dated and shall include a written determination by the TPI of Code compliance or noncompliance.

F. Each Inspection Report shall include the time and date of inspections, the stage of the planned construction and shall be signed by the TPI conducting the inspection.

Disclaimer: These regulations may not be the most recent version. Maine may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.