Code of Maine Rules
16 - DEPARTMENT OF PUBLIC SAFETY
642 - BUREAU OF BUILDING CODES AND STANDARDS
Chapter 2 - MAINE UNIFORM BUILDING CODE AND UNIFORM ENERGY CODE - THIRD PARTY INSPECTORS ("TPI")
Section 642-2-5 - CONSTRUCTION FILE

Current through 2024-13, March 27, 2024

1. One copy of the Construction File shall be retained by the TPI, and an additional copy shall be furnished to the municipality when the Application for Certificate of Occupancy is submitted.

2. One copy of the Construction File shall be provided to the Applicant and shall be available upon request, for inspection, during the planned construction.

3. The Construction File shall contain the following:

A. All written correspondence between the TPI and the Applicant regarding the planned construction. The inclusion of contractual documents regarding contracted services by and between the TPI and Applicant is voluntary.

B. A copy of the plans, schematics, diagrams, and specifications fully describing the planned construction.

C. A copy of the Notice to Proceed issued by the TPI to the Applicant for the planned construction.

D. Change orders for significant modification of planned construction and TPI approval for each change order.

E. A copy of all inspection reports prepared by the TPI.

F. A copy of all photographs of the construction. Each photograph shall be time dated.

G. A final statement of the TPI to the municipality advising if the subject construction is compliance with these Codes.

Disclaimer: These regulations may not be the most recent version. Maine may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.