Code of Maine Rules
16 - DEPARTMENT OF PUBLIC SAFETY
642 - BUREAU OF BUILDING CODES AND STANDARDS
Chapter 2 - MAINE UNIFORM BUILDING CODE AND UNIFORM ENERGY CODE - THIRD PARTY INSPECTORS ("TPI")
Section 642-2-5 - CONSTRUCTION FILE
Universal Citation: 16 ME Code Rules ยง 642-2-5
Current through 2024-13, March 27, 2024
1. One copy of the Construction File shall be retained by the TPI, and an additional copy shall be furnished to the municipality when the Application for Certificate of Occupancy is submitted.
2. One copy of the Construction File shall be provided to the Applicant and shall be available upon request, for inspection, during the planned construction.
3. The Construction File shall contain the following:
A. All written correspondence
between the TPI and the Applicant regarding the planned construction. The
inclusion of contractual documents regarding contracted services by and between
the TPI and Applicant is voluntary.
B. A copy of the plans, schematics, diagrams,
and specifications fully describing the planned construction.
C. A copy of the Notice to Proceed issued by
the TPI to the Applicant for the planned construction.
D. Change orders for significant modification
of planned construction and TPI approval for each change order.
E. A copy of all inspection reports prepared
by the TPI.
F. A copy of all
photographs of the construction. Each photograph shall be time dated.
G. A final statement of the TPI to the
municipality advising if the subject construction is compliance with these
Codes.
Disclaimer: These regulations may not be the most recent version. Maine may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.