Current through 2024-38, September 18, 2024
A.
TREATMENT TANKS, DOSING TANKS, AND GREASE INTERCEPTORS
1. Scope: This Section governs the design,
installation, repair, and maintenance of septic tanks, aerobic treatment tanks,
dosing tanks, grease interceptors, post-septic tank effluent filters, and
piping.
2. Abandoned septic tanks:
The property owner or property owner's agent is responsible for seeing to it
that the contents of all abandoned septic tanks are pumped and disposed of
properly. The top or entire septic tank must be removed and the remaining
portion of the septic tank or excavation must be filled immediately.
B.
SEPTIC TANK
REQUIRED
Wastewater must be treated by an approved septic tank prior
to being discharged into a disposal field, unless the applicant receives a
primitive system permit, as described in Section
5 or a holding tank permit as
described in Sections
9 and
10. The use of an aerobic treatment
unit or any other device in lieu of, or in conjunction with, a septic tank not
be permitted by the LPI without prior approval of the device by the
Department.
C.
SEPTIC
TANK CONSTRUCTION MATERIALS
1. General:
Septic tanks may be constructed of the following materials: reinforced
poured-in-place concrete, precast reinforced concrete, fiberglass, or
polyethylene. Each septic tank model must be approved by the Department. Metal
septic tanks are prohibited.
2.
Concrete: Concrete used in the construction of septic tanks must meet the
American Concrete Institute (ACI) standards for frost resistance (ACI
318-16-4.5.1) and water-tightness (ACI 318-16-4.5.2).
3. Fiberglass: Prefabricated fiberglass
septic tanks must meet the American Society for Testing and Materials (ASTM)
Standard ASTM D4021.
4.
Polyethylene: Prefabricated polyethylene septic tanks must meet the
requirements of the Canadian Standards Association (CSA) Standard B66-10, or
the most current edition of the CSA tank standard. Prefabricated polyethylene
septic tanks must be listed in the CSA records as CSA certified.
D.
SEPTIC TANK
DIMENSIONS
1. Liquid depth: When the
tank is filled to its maximum capacity, the depth of the liquid in the septic
tank must be at least 30 inches.
2.
Air space: The interior distance between the top of the outlet pipe tee or
baffle and the top of the septic tank must be at least 1 inch.
3. Configuration: Tanks must be constructed
such that the direction of flow is along the longest inside
dimensions.
4. Rectangular septic
tanks: The inside length, measured from inside wall to inside wall, must not be
less than 74 inches.
5. Cylindrical
septic tanks: Upright cylindrical septic tanks must have a minimum diameter of
52 inches. Horizontal cylindrical septic tanks must have a minimum length of 72
inches. Their minimum width at the maximum liquid level must be 36
inches.
E.
INLET
AND OUTLET CONNECTIONS
1. General:
Inlet and outlet connections of each septic tank or compartment must be
designed to obtain effective retention of scum and sludge. All connections and
baffles must be fastened with and constructed of, or coated with, materials
that are resistant to corrosion. Where pipe tees are used, the pipe tees must
be sanitary pipe tees and installed in a manner that provides a lasting
watertight seal between the pipe tee and the wall of the septic tank. To obtain
a watertight seal, a manufactured waterproof coupling may be incorporated into
the wall of the septic tank. Expanding grout that will adhere both to the pipe
tee and to the body of the septic tank where the pipe tee is installed may be
used instead.
2. Baffles: A baffle
or pipe tee not less than 4 inches in diameter is required at both the inlet
and the outlet of a septic tank. The bottom of the baffle or of the vertical
leg of the pipe tee at the inlet end of the tank must extend below the maximum
liquid level at least 20 to 30% of the total liquid depth. The baffle or pipe
tee at the outlet must extend from within 1 or 2 inches of the top of the tank
to at least 16 inches below the maximum liquid level. It must block the outlet
so that solids and scum cannot exit from the tank. A septic tank filter may be
used in lieu of the outlet baffle.
3. Inlet connections: The invert elevation of
the septic tank inlet must be at least 2 inches higher than the invert
elevation of the septic tank outlet or the outlet of the first compartment. The
inverts of the inlets of subsequent compartments must be at least 1 inch above
their outlets. When a baffle is used, the inlet pipe must be flush with the
inside wall of the tank to prevent a buildup of solids between the inlet and
the baffle.
4. Outlet connections:
Outlet connections must be permanently fastened in place.
F.
ACCESS OPENINGS FOR ALL SEPTIC AND
PRE-TREATMENT TANKS
1. All septic
tanks: Access openings for septic tanks must meet the following requirements:
a. Minimum access opening: All septic tanks
must be constructed to provide an access to each tank compartment. Each access
must be: at least 18 inches along the side, if square; at least 18 inches in
diameter, if round; and as nearly as possible centered over the
compartment.
b. Additional
openings: Additional inspection openings, at least 6 inches square or 6 inches
in diameter, must be located on the top of the tank directly above the tank
inlet and outlet connections.
2. Single-family dwelling units: Access
opening for septic tanks serving single-family dwelling units must meet the
following requirements:
a. Access openings:
Access openings for all septic tanks are required to have a minimum of one
watertight riser to finish grade in order to simplify location and maintenance.
The riser must be located at the appropriate opening to facilitate pumping. The
riser opening must be at least 18 inches in diameter over the tank cover. The
pump station riser is required to extend to finished grade and must be sized to
accommodate removal and installation of any pump(s) within the tank. Outlet
baffles that utilize an effluent filter must have a riser of at least 18 inches
in diameter extended to finish grade. Other risers may terminate to within 6
inches of finished grade.
b. Septic
tank covers: Septic tank covers must be removable and flush with the tank top.
Concrete tank covers must be chamfered on all edges. They must have a steel
lifting loop equal to a #2 reinforcing bar, which is cast in place and projects
enough for a 1 and 1/2-inch diameter object to pass through the loop. Tank
covers made from other materials must be lift-out, screwed, or
bolted.
3. Other
facilities: Access to all septic tanks serving facilities other than single
family dwellings must be located at grade as described in this Section. Grade
must slope away from the openings.
a.
Compartment manholes: Manholes must have a watertight riser of the same
material as the tank. Use H-20 construction in traffic areas. Provide bolted,
gas tight, or locking covers where appropriate.
4. Garbage disposal: Garbage disposals should
not be used with disposal fields. However, if such units are proposed to be
used, other measures must be taken, such as:
a. Increasing septic tank capacity by a
minimum of 30 percent;
b. The
installation of a second septic tank installed in series; or a multiple
compartment septic tank (specified in Section
7(G)(6);
c. The use of septic tank outlet filters;
and
d. Must be included in the
system design to prevent suspended solids from entering the disposal
field.
G.
LIQUID CAPACITY OF SEPTIC TANKS
1. The minimum liquid capacity of the septic
tank(s) serving 1 to 3-family dwelling units must meet the capacity
requirements of Table 7A for each dwelling unit. For example, a duplex
comprised of one two-bedroom unit and one three-bedroom unit would require a
septic tank capacity of 1,750 gallons.
2. Septic tank size for other than 1 to
3-family dwelling units: When serving structures other than 1 to 3-family
dwelling units, the liquid capacity must be a minimum of 150 percent of the
design flow prescribed in Section 5, or as specified in Section
7(G)(3), whichever is
greatest.
3. Minimum septic tank
size: The minimum liquid capacity of an individual septic tank must be 750
gallons for any use.
4. Septic
tanks for engineered systems: Multiple compartment or multiple septic tanks are
required for institutional and commercial installations where the design flow
(determined as prescribed in Section
5 is greater than 2,000 gallons.
TABLE 7A
SEPTIC TANK CAPACITY
FOR DWELLING UNITS
Number of bedrooms per
Unit
|
Minimum septic tank liquid
capacity per Unit
|
1 Bedroom
|
750 gallons
|
2 Bedrooms
|
750 gallons
|
3 Bedrooms
|
1,000 gallons
|
4 Bedrooms
|
1,000 gallons
|
5 Bedrooms
|
1,250 gallons or
|
For each additional
|
250 gallons per bedroom
|
5.
Multiple septic tanks: 2 or more septic tanks may be connected in series to
obtain the minimum required liquid capacity. When different size septic tanks
are used, the greater capacity must be first in the series.
6. Multiple compartment septic tanks:
Multiple compartment septic tanks must meet the following requirements:
a. Minimum liquid capacity: The total liquid
capacity of the multiple compartment tank must be at least 750
gallons;
b. Sizing the first
compartment: The first compartment must have a minimum liquid capacity at least
66 percent of the total required liquid capacity, determined pursuant to
Section 7(G)(2);
c. Number of compartments: Septic tanks with
total liquid capacities of less than 1,250 gallons may have only 1 or 2
compartments, while septic tanks with total liquid capacities greater than
1,250 gallons may have more than 2 compartments; and
d. Connecting compartments or multiple septic
tanks: Multiple compartments may be provided by connecting individual septic
tanks in series. Where a single partitioned septic tank is used, vent holes
must be installed near the top of each partition to allow free exchange of
evolved gases between compartments. The 2 compartments must be connected by
means of a pipe tee, baffle, or septic solids
retainer.
H.
TANK INSTALLATION
1. Fill
requirements for tank installations: The fill material around septic tanks,
dosing tanks, holding tanks, aerobic treatment tanks and external grease
interceptors must be free of large stones, roots, or foreign objects. It must
be placed in layers and must be thoroughly tamped in a manner that will avoid
undue strain on the septic tank. For prefabricated plastic or fiberglass septic
tanks, the fill material must not be thicker than the thickness recommended by
the manufacturer.
2. Minimum
setback distances: Septic tanks must be located with a minimum distance between
system, structure(s), and any other site elements pursuant to first-time system
criteria or replacement system criteria, as appropriate.
3. Anti-flotation: The site evaluator must
include in the design provisions to prevent the tanks from floating, if
empty.
4. Leakage: Provisions must
be made to prevent surface and subsurface water from entering the
tanks.
5. Traffic loading: When
tanks are installed under a driveway, parking lot, or other areas subject to
heavy loads, the tanks must be able to withstand an American Association of
State Highway Transportation Officials (AASHTO) H-20 wheel load.
6. Bedding: All tanks must be bedded on a
4-inch minimum layer of clean sand, gravel, or stone. The bedding material must
extend at least 4 inches beyond the base of the tank.
7. Level and accessible: All tanks must be
set level and, if an elevation and location is specified on the HHE-200 Form,
at that elevation. Tanks must be readily accessible for maintenance and
cleaning.
8. Testing: All tanks
with a seam below the outlet invert installed 50 feet or less from the high
water mark of a major water body/course or a private potable water supply, or
less than 150 feet from a public water supply, must be tested in place,
according to the following procedure:
a. The
tank is to be filled with water to the outlet invert;
b. After 24 hours, the water level must be
topped off to the outlet invert;
c.
After 4 hours, the depth from the water surface to the top of the outlet invert
is measured. If the value is 1 inch or less, the tank is deemed water
tight.
I.
MAINTENANCE AND SLUDGE DISPOSAL
1. Maintenance: Septic tanks and other
treatment tanks must be regularly maintained. As a general rule, the tank
contents must be removed whenever the sludge and scum occupies one-third of the
tank's liquid capacity.
2. Septage
disposal: All septage must be disposed of at a location approved by the Maine
Department of Environmental Protection.
J.
DOSING TANKS
1. General: All dosing tanks must be
watertight. Materials and construction specifications are the same as those
specified for septic tanks in this Section. Manholes for dosing tanks must
terminate a minimum of 4 inches above the ground surface.
2. Frost protection: In cases where the
dosing tanks will be installed above the maximum expected depth of frost
penetration, dosing tanks must be protected with at least 2 inches of high
density expanded rigid polystyrene.
3. Dosing compartments: When a dosing
compartment is located inside a septic tank, the dosing compartment must not
reduce the minimum tank liquid capacity required in Section
7(G).
4. Access openings: Access openings for
dosing tanks may be buried, although are required to have watertight risers to
finish grade, in order to simplify location and maintenance. The riser opening
must be at least 18 inches in diameter and must be sized to accommodate removal
and installation of any component(s) within the tank.
K.
AEROBIC TREATMENT UNITS
1. General: The use of an aerobic treatment
unit or any other device in lieu of, or in conjunction with, a septic tank must
not be permitted by the LPI without prior approval of the device by the
Department. Any aerobic treatment tank used in lieu of, or in conjunction with,
a septic tank must bear the endorsement of the National Sanitation Foundation's
Standard 40, or other endorsement accepted by the Department; or review and
approval from the Department.
2.
Use of an aerobic treatment unit allows disposal area size modification
pursuant to Section
5(H).
L.
EXTERNAL GREASE INTERCEPTORS
1. General: Any new commercial or
institutional food preparation facility, such as a restaurant, cafeteria,
institutional kitchen, or other facility subject to Footnote 2 of Table 5C,
served by a subsurface wastewater disposal system, must install an external
grease interceptor.
2. Any
converted or expanded commercial or institutional food preparation facility
requires an external grease interceptor, except when not practical, as
determined by the LPI. In such a case, an internal grease interceptor must be
used, meeting the requirements of the Plumber's Examining Board Installation
Standards, 02-395 CMR 395 or, if the design flow of the facility is 100 gpd or
less, a high efficiency outlet filter may be installed in the septic tank, in
lieu of an external grease interceptor.
3. Location: The external grease interceptor
must be installed in a separate line serving that part of the plumbing system
into which the external grease will be discharged. The external grease
interceptor must be located close to the source of the wastewater (to keep the
grease from solidifying). External grease interceptors must be installed with
an access cover to the surface and located, designed and installed in a manner
that will permit easy access for inspection, repair, and cleaning.
4. Sizing the external grease interceptors
for restaurants: Equation 7B must be used to determine the minimum size of
external grease interceptors serving restaurants.
5. Sizing the external grease interceptors
for cafeterias and institutional kitchens: Equation 7B must be used to
determine the minimum size of external grease interceptors serving cafeterias
and institutional kitchens.
Equation 7B
Q=[M][GL][ST][LF]
Where:
Q is the liquid capacity of external
grease interceptor, gallons;
M is the total number of meals served
per day;
GL is the gallons of wastewater per
meal, typ. 2.0 gallons;
ST is the storage capacity, typ. 2;
and
LF is a loading factor depending on type
of facilities present:
LF is 1.0 with dish washing; and;
LF is 0.5 without dish
washing. |
6.
Minimum size: In no case may an external grease interceptor serving a
restaurant, cafeteria, or institutional kitchen be smaller than 750 gallons
liquid capacity.
7. Construction:
The minimum requirements for construction, materials, and foundations of
external grease interceptors are the same as those required for septic tanks.
The installation must be in accordance with 6(H).
8. Outlet baffle of grease trap: The outlet
of the external grease interceptor must be provided with pipe tee baffle
extending to a depth of 12 inches above the tank floor and well above the
maximum liquid level. A septic tank filter may be used in lieu of the outlet
baffle.
9. Maintenance: All
external grease interceptors must be routinely inspected to determine the
volume present. All external grease interceptors must be cleaned when the
volume of external grease equals no more than 50 percent of the liquid capacity
of the tank.
M.
PIPING
1. Scope: This Section
governs the design and installation of the piping systems used to convey
wastewater from the building drain to the septic tank, to the disposal field
and within the disposal field.
2.
Methods of distribution: The allowed methods for discharge of septic tank
effluent to the disposal field and distribution of septic tank effluent within
the disposal field are as follows:
a. Gravity
flow method;
b. Gravity dosing
method;
c. Low pressure dosing
method; and
d. Serial dosing
method.
3. Alternating
pumps: Alternating pumps may be used to alternately dose a field or portion of
a field. However, no disposal field or portion of a disposal field may receive
more than the maximum daily disposal design flow allowed in Section
5. Alternating pumps must be installed
in pump-dosed systems with design flows of more than 2,000 gpd.
4. Connecting Pipes and Delivery Pipes: The
connecting pipes between the components of a system must meet the following
requirements:
a. Gravity flow piping: The
pipes must be sized to serve the connected components, but in no case may be
less than 3 inches in diameter (1.5 inches for primitive systems);
b. Pump discharge piping: The pipes must be
sized to serve the pump but in no case may have a diameter less than that
required by the manufacturer.
c.
Siphon discharge piping: The pipes from dosing tanks using siphons must be one
nominal pipe size larger than the siphon to facilitate venting.
5. Piping materials: Pipes must be
constructed of:
a. Plastic pipe: Polyvinyl
Chloride plastic (ASTM D2665), Schedule 40, SDR-21, SDR-26, or SDR-35; or
Acrylonitrile-Butadiene-Styrene plastic (ASTM 2661); or Polyethylene, straight
wall (ASTM D-1248);
b. Iron pipe:
Ductile cast-iron; or
c. Other
pipe: Other material permitted by the Department.
6. Joints: All pipe joints must be made
watertight.
7. Bedding the pipe:
Pipes must be laid on a firm foundation. Pipes must be protected from freezing
if there is any possibility of liquid remaining in the pipes.
8. Cleanouts: At least one cleanout must be
provided for every 100 feet of connecting pipe in a gravity system.
9. Alignment and grade: The alignment and
grade of connecting pipes must meet the following requirements:
Minimum pitch: Connecting pipes must have a minimum grade as
follows:
a. Building sewer: The
minimum pitch of the building sewer is " inch per foot (2 percent). For pipes 4
inches in diameter or larger, 1/8-inch per foot (1 percent) may be authorized
by the LPI. The building sewer may not be smaller in diameter than the building
drain.
b. Effluent line (gravity):
The minimum pitch of the gravity effluent line is 1/8-inch per foot (1
percent).
c. Pipe alignment:
Connecting pipes must be laid in a continuous grade and as nearly as possible
in a straight line. Drop manholes may be installed if found necessary.
Horizontal bends, where required, must not be sharper than 45 degrees. The
inside angle between adjacent sections of pipe must be no less than 135
degrees.
10. Frost
protection: In cases where the delivery pipe from the dosing tank will be
installed higher than the maximum expected depth of frost penetration, the
design shown in the application for a disposal system permit must specify
either that the delivery pipe will drain at the end of each dosing cycle or be
provided with a minimum of 2 inches of high-density expanded rigid polystyrene
insulation, or otherwise be protected from frost.
11. Separation of a structure's water service
and building sewer: A structure's water service pipe and the building sewer
must be separated by undisturbed or compacted earth. The water service pipe may
only be placed in the same trench as the building drain and building sewer when
installed in compliance with the following requirements:
a. Minimum vertical separation: The bottom of
the water service pipe at all points must be a minimum of 12 inches above the
top of the sewer at its highest point;
b. A separate shelf for water service: The
water service pipe must be placed on a solid shelf excavated at one side of the
common trench; and
c. Piping
requirements: The drainage pipe must conform to one of the standards for ABS
plastic pipe, ductile cast iron pipe, or PVC plastic pipe listed in Table
7HI.
12. Separation
between public water main and building sewer: A building sewer or force main
must be at least 10 feet horizontally from any existing or proposed public
water main, measured edge to edge. In cases where it is not practical to
maintain a 10-feet separation, the design shown in the application for a
disposal system permit must insure that a leak in the building sewer will not
contaminate the public water main. The allowed methods for protecting public
water mains are described below:
a. Separate
trenches: The building sewer is laid in a separate trench, or
b. Same trench: If the building sewer and
public water main are in the same trench, the public water main must be on an
undisturbed earth shelf at such an elevation that the bottom of the public
water main is at least 18 inches above the top of the building sewer. Concrete
encasement of the building sewer joints is required.
13. Building sewer crossing a public or
private water main: When a building sewer or force main crosses a public or
private water main, the design shown in the application for a disposal system
permit must insure that a leak in the building sewer will not contaminate the
water main. The allowed methods for protecting water mains are described below:
a. Gravity building sewer: One 10-foot length
of building sewer pipe must be located, so that both joints will be as far from
the water main as possible. The building sewer must be supported to prevent
sagging and damage from backfilling. It must be protected from
freezing.
b. Force main: At least
10 feet of the force main perpendicular to the water main must be encased in a
second sewer pipe of like material with the ends sealed with concrete. The
force main must be supported to prevent sagging and damage from backfilling. It
must be protected from freezing.
N.
DISTRIBUTION PIPES
1. Gravity flow and gravity dose distribution
networks: Gravity flow and gravity dosing distribution networks may consist of
a single distribution pipe, two or more distribution pipes connected by means
of elbows or tees, or two or more separate distribution pipes connected
independently to a distribution box. Distribution pipes must meet all the
requirements of this Section.
2.
Minimum diameter: Distribution pipes must be a minimum of 3 inches in diameter
(2 inches for primitive systems, and not to exceed 2 inches).
3. Piping: Distribution pipes must consist of
lengths of rigid, perforated pipes connected with tight joints. Individual runs
of distribution pipe must be capped at the end, unless the pipes are to be
connected together by loops, header pipe, overflow pipe, or other
cross-connections as specified by the system design plans.
4. Perforations: There must be two rows of
evenly spaced perforations running the length of the distribution pipe. The
rows must be on each side of the pipe, midway between the invert and the center
line that separates the upper and lower halves of the pipe; i.e., at the 4
o'clock and 8 o'clock positions. Perforations must be no smaller than 3/8 inch
and no larger than " inch in diameter.
5. Pitch: Each individual distribution pipe
must be set level, not to exceed a slope of 2 inches in 100 feet.
6. Spacing: The distance between pipes must
be no greater than 5 feet and no less than 1 foot. Pipes must be no more than 5
feet and no less than 1 foot from the sidewalls.
7. Pipe material: The following materials are
acceptable for distribution pipes: Plastic pipe meeting the following:
Acrylonitrile-Butadiene-Styrene (ASTM D-2751); Polyvinyl Chloride (ASTM D-2729,
D-3034); Styrene-Rubber (ASTM D-2852, D3298); or Polyethylene, straight wall
(ASTM D-1248).
O.
DISTRIBUTION BOXES
1. General: The use
of distribution boxes is optional but is encouraged to allow access for
maintenance and troubleshooting purposes.
2. Construction: Distribution boxes must be
constructed of sound and durable materials that will resist decay or corrosion,
frost damage, cracking, or buckling due to backfilling or other anticipated
stresses.
3. Installation: The
distribution box must be set perfectly level, on a firm base, carefully
backfilled to prevent settlement or other movements and must be installed as
follows:
a. Disposal fields: When possible,
the distribution box should be installed directly on the disposal field stone
to minimize frost disturbance.
b.
Minimum footings: For engineered systems, the distribution box must be set on a
layer of gravel or on a concrete footing extending downward below the maximum
expected depth of frost penetration. Where gravel is used, the gravel must
extend laterally a minimum of 6 inches beyond the side of the distribution box,
meet the gradation specifications of the Maine Department of Transportation
Standard Specifications - Revision of December 2002 " Section
700" Materials 703.06 Aggregate for
Base and Sub-base, and must be compacted to 95 percent modified proctor per
ASTM D2940 - 03 Standard Specification for Graded Aggregate Material For Bases
or Sub-bases for Highways or Airports.
4. Outlets: A separate outlet must be
provided for each distribution pipe. The inverts of all outlets must be rigidly
set at the same level a minimum of 1 inch above the bottom of the distribution
box. When installation is complete, the distribution box must be filled with
water, at which time the installation must be checked to make sure that it is
level. Check to make sure that the water rests equally at the invert of each
pipe. Necessary adjustments must be made to ensure that all outlets are
permanently and securely fixed at exactly the same elevation prior to
backfilling.
5. Inlets: For
gravity-fed distribution boxes, the invert of the inlet must be at least 1 inch
above the invert of the outlets. When dosing is employed or when the connecting
pipe from the septic tank has a steep slope, measures must be taken to prevent
direct flow of septic tank effluent across the distribution box outlets. This
direct flow may be prevented by installing a baffle or elbow to direct the flow
to the bottom of the box within the distribution box, by connecting the inlet
to the bottom of the distribution box, or by using two distribution boxes
connected in series. In the latter case, all outlets of the first distribution
box must be sealed off, except for the outlet that discharges to the second
distribution box.
6. Access:
Distribution boxes must be provided with a means of access. In the case of
smaller boxes, access may be made by a removable lid. Access to larger boxes
may be provided by means of manholes and inspection ports with removable,
watertight covers. In all cases, the following requirements must be met:
a. Size and location: Access openings must be
adequate in size and located to facilitate removal of accumulated solids and
inspection of the inlet and all outlets.
b. Access opening extensions: All access
openings must be extended to within 12 inches of the finished grade
surface.
c. Water-tightness: Access
openings must be constructed in a manner that prevents the entrance of
water.
7. Frost
protection: In cases where the distribution boxes will be installed higher than
the maximum expected depth of frost penetration, distribution boxes must be
protected by a minimum of 2 inches of high density expanded rigid polystyrene
to give protection against frost penetration. In addition, entering through the
bottom of the distribution box is recommended to prevent freezing associated
with forced main inlets.
P.
DROP BOXES
1. General: The use of drop boxes is
optional. Drop boxes provide an effective way to assure that serial
distribution disposal fields are properly loaded. They also provide a means for
monitoring the water levels in respective disposal fields. When drop boxes are
used:
a. Overflow elevation: The overflow pipe
to the next disposal field must be installed so that the upper disposal field
is full to the invert of the distribution piping of septic tank effluent before
flow spills over to the next disposal field being served from the
box;
b. Overflow piping: The
overflow pipe between drop boxes must be watertight. Drop boxes must be placed
in a trench dug only deep enough to allow connection to the next lower drop
box. The soil backfilled around the overflow pipe must be carefully compacted
below and around it to prevent seepage along the pipe between disposal field
laterals;
c. Installation: The drop
boxes must be set on a firm base and carefully backfilled to prevent settlement
or other movements; and
d. Bypass
capability: The drop boxes must be of such design that a disposal field lateral
can be removed from service and the flow shunted to the next disposal field
lateral, if necessary.
2.
Frost protection: In cases where the drop boxes will be installed higher than
the maximum expected depth of frost penetration, the design shown in the
application for a disposal system permit must specify that drop boxes are
surrounded by 2 inches of high-density expanded rigid polystyrene, to protect
against frost penetration and freezing.
Q.
DOSING TANKS FOR ENGINEERED
SYSTEMS
1. When required: If a dosing
tank with a siphon or pump is required for engineered systems using gravity or
low-pressure dosing, it must meet the requirements of this Section.
2. Minimum liquid capacity: The minimum
liquid capacity of dosing tanks using pumps must be determined as follows:
a. Minimum capacity: Dosing tanks using pumps
must have sufficient liquid capacity to distribute septic tank effluent equally
to all parts of the disposal field during each dosing cycle. They must also
provide adequate reserve storage capacity (at least equal to the minimum dosing
volume) in the event of a pump malfunction. The total liquid capacity must be
great enough to accommodate the minimum required dose volume, plus the minimum
required reserve storage capacity determined as prescribed in Section
7(Q)(3). Additional
volume must be provided above the pumping level to accommodate the volume of
water displaced by the pump and controls, as well as any quantity of septic
tank effluent that will drain back into the dosing tank when the pump shuts off
at the end of a dosing cycle. To summarize, minimum dosing tank capacity is the
sum of dose volume, reserve storage, pump and control displacement, and
effluent drain-back.
b. Solid
storage: Additional volume must be provided below the pumping level so that the
pump may be placed on a pedestal, above the dosing tank bottom, to prevent the
pump from drawing in air or whatever solids may accumulate in the bottom of the
dosing tank.
3. Reserve
capacity when using pumps: Reserve capacity is the inside volume of the dosing
tank that lies between the level at which the high-water alarm switch is set
and the invert elevation of the tank inlet. A minimum reserve capacity equal to
the design flow is required except where a standby pump is provided that is
equivalent in performance capacity to the primary pump and that will switch on
automatically in the event that the primary pump malfunctions.
4. Dose volume and minimum reserve capacity:
The dose volume and minimum reserve capacity for gravity-dosed disposal fields
must be 15 to 25 percent of the design flow, the pump dose off-switch must be
at least 6 inches above the pump intake.
5. Dosing tanks using a single siphon: The
liquid capacity of dosing tanks using siphons must be adequate to provide the
required dose volume determined as prescribed in Section
7(Q)(4). No reserve
capacity is required when a siphon is used.
6. Requirements for all dosing tanks: All
dosing tanks must meet the following requirements regardless of whether a pump
or siphon is used.
a. Construction: The
requirements for the construction of dosing tanks must comply with those
prescribed for septic tanks in Section
10. Dosing tanks may be constructed
as a separate unit or may share a common wall with the septic tank.
b. Installation: Installation requirements
for prefabricated dosing tanks must comply with those for septic tanks, as
prescribed in Section
7(H).
c. Inlet elevation: Inlets must be at least 1
inch above the highest water level attained when the entire reserve capacity is
full.
d. Access openings: Dosing
tanks must be readily accessible for service and repair and require risers to
grade.
7. Backfilling:
Requirements for backfilling around dosing tanks are the same as for septic
tanks, specified above.
R.
SPECIFIC REQUIREMENTS FOR DOSING
WITH SIPHONS
1. General: Dosing may be
accomplished by means of an automatic siphon when the low water level in the
dosing tank is at a higher elevation than the invert of the highest
distribution pipe. All requirements in this Section must be met.
2. Siphon tank outlets: Outlets for dosing
tanks using siphons must conform to the manufacturer's
recommendations;
3. Corrosion
control: Siphons must be constructed of durable materials not subject to
corrosion by acid or alkali;
4.
Sizing dosing tanks: The horizontal dimensions of the dosing tank must be
adjusted, so that the volume obtained by multiplying the manufacturer's rated
siphon drawing depth by the internal horizontal area of the dosing tank will be
equal to the required dose volume determined, as prescribed in Section
7(Q) 6; and
5. Starting siphons: When installation is
complete, the siphon must be primed and checked in the presence of the LPI by
filling it with water. At this time, the siphon must be checked for leaks, as
evidenced by air bubbles rising from the bell casing or piping. Any leaks must
be repaired before final approval is given.
6. Gravity dosing: In gravity dosing systems,
when the delivery pipe between the dosing tank and the distribution box or
distribution network is long, the siphon invert must be set at an elevation
sufficiently higher than the invert of the highest distribution pipe to
compensate for any head losses due to friction in the connecting pipe. Friction
head must be determined using Table 7I.
7. Low pressure dosing: In low pressure
dosing systems, the invert of the siphon must be set higher than the invert of
the distribution pipes by a distance equal to the total operating head. See
EPA's On-site Wastewater Design Manual for additional
guidance.
8. Peak inflow check: For
facilities from which large quantities of septic tank effluent may be
discharged at one time, the designer must make certain that the siphon
discharge rate will not be exceeded by the maximum expected rate of inflow at
time of peak volume.
9. Cycle
counter: Each siphon-equipped dosing tank must employ a cycle counter,
activated by a weighted float or switch, to monitor siphon
performance.
10. High water alarm:
Dosing tanks using siphons must be equipped with an overflow to the
distribution box (or distribution network) and a high-water alarm meeting the
requirements for holding tanks. The invert of the overflow must be just above
the level of the high-water alarm switch which, in turn, must be several inches
above the normal high-water level of the dosing tank.
S.
SPECIFIC REQUIREMENTS FOR DOSING
WITH PUMPS
1. General: Dosing may be
accomplished by means of a pump when either gravity dosing or low-pressure
dosing is used. All requirements in this Section must be met.
2. Duplicate pumps required: Duplicate pumps
are required for systems serving multifamily residential structures or
systems.
3. Pump rating: The pump
must be rated by the manufacturer to handle septic tank effluent.
4. Minimum pump performance: Pumps used for
gravity dosing systems must be rated by the manufacturer (as indicated by the
manufacturer's pump performance curve) to be capable of delivering the total
required dose volume within a period of 15 minutes or less when working against
a total dynamic head equal to the total design operating head. For the purpose
of making this determination, the total design operating head must be
considered as the sum of the elevation head and the friction head calculated
using Table 7I.
5. Pump selection
for low pressure dosing: Selection of an adequate pump for low pressure dosing
is part of the design procedure for low pressure dosing systems.
6. Solid storage: Pumps must be set on a
pedestal or have legs, so that the intake is elevated several inches above the
bottom of the dosing tank.
7.
Couplings: Easy or "quick disconnect" couplings should be used to facilitate
removal of the pump for servicing.
8. Peak inflow check: For facilities from
which large quantities of septic tank effluent may be discharged at one time,
the design must make certain that the pump discharge rate will not be exceeded
by the maximum expected rate of inflow at times of peak volume.
9. Pump switches: The operation of the pump
must be controlled by means of automatic switches that are activated by the
rising and falling level of septic tank effluent in the dosing tank. Such
switches must meet the following requirements:
a. Switches: Switches must be able to
withstand the humid and corrosive atmosphere in the dosing tank. Mercury or
weighted float type switches are suitable for this purpose. Pressure diaphragm
type switches are prohibited.
b.
Dose volume: For single-family dwellings the dose volume for gravity-dosed
disposal fields must be as per manufacturers" specifications.
10. High-water alarm: A high-water
alarm switch must be set 4 inches above the pump-on switch and must activate
visible and audible alarms that can be readily seen and heard by occupants
within the structure served. The high-water alarm switch must meet the
requirements prescribed for pump-control switches Section
7(S)(9)(a). The alarm
and its switch must not be on the same electrical circuit as the pump and its
switch.
T.
VENTING
1. General: Vents are not
required (unless required by the component manufacturer) but may be used in
disposal systems. If used, vents should meet the following design and
construction standards:
a. Location: A vent
should be installed in the distribution system at a point or points farthest
from the septic tank;
b. Size: A
vent diameter should be equal to or greater than the diameter of the dosing
piping;
c. Height: A vent must
extend at least 3 feet above the finished grade; and
d. Protection: All vents should be screened
to prevent entry of foreign objects and installed in a manner which prevents
entry of rainwater.
U.
MANUFACTURED DISPOSAL AREAS
1. General: Approved proprietary disposal
devices may be used in lieu of a stone filled disposal field. A potential
purchaser is advised to obtain information pertaining to the relative cost,
availability, installation procedures, method of wastewater distribution, and
specific design considerations.
2.
Requirements: The use of proprietary disposal devices may be approved, provided
they meet the following conditions:
a. The
square footage of the bottom and sidewall area of proprietary disposal devices
varies from one manufacturer to another. Therefore, the required number of
proprietary disposal devices from a specific manufacturer is determined by
dividing its standard stone-filled square-footage equivalent into the total
bottom and sidewall area, determined by multiplying the appropriate minimum
hydraulic loading rate, from Table 5E and the design flow, from Section
5;
b. When proprietary disposal
devices are used in a cluster configuration, only the unshielded bottom area
can be used to determine its standard stone-filled disposal-field
equivalent;
c. When proprietary
disposal devices are used in a trench configuration, only the sum of its
unshielded bottom and sidewall area can be used to determine its standard
stone-filled disposal-field equivalent;
d. The number of proprietary disposal devices
must be rounded up to the nearest whole disposal device;
e. The separation distance between groups of
proprietary disposal devices is identical to the distances required for a
standard stone filled disposal field;
f. Gravity, low pressure, or serial
distribution may be used;
g.
Proprietary disposal devices must be installed level and must be bedded and
covered per each manufacturer's recommendations; and
h. In all other respects, each proprietary
disposal device installation must comply with this rule.
V.
CONCRETE DISPOSAL
DEVICES
1. Manufacturers: Manufacturers
must be approved by the Department.
2. Sizing requirements for 4-foot-by-8-foot
disposal devices: When used in clusters, the disposal fields are sized
according to bottom area only. Each 4-foot-by-8-foot disposal device has an
effective disposal infiltration area of 64 square feet.
a. When used in trenches with one foot of
stones along the 4-foot sidewalls, each 4-foot-by-8-foot disposal device has an
effective disposal infiltration area of 77 square feet. A separation distance
of 3 feet from edge of stone to edge of stone is required when used in trench
configuration.
b. When used in
trenches with one foot of stone along the 8-foot sidewalls, each
4-foot-by-8-foot disposal device has an effective disposal infiltration area of
90 square feet. A separation distance of 3 feet from edge of stone to edge of
stone is required when used in trench configuration.
3. Sizing requirements for 8-foot-by 8-foot
disposal devices: When used in clusters, each 8-foot-by-8-foot disposal device
has an effective disposal infiltration area of 128 square feet. When used in
trenches with one foot of stone along two sidewalls, each 8-foot-by-8-foot
disposal device has an effective disposal infiltration area of 154 square feet.
A separation distance of 3 feet from edge of stone to edge of stone is required
when used in trench configuration.
4. Sizing requirements for 4-foot-by 10-foot
disposal devices: When used in clusters, each 4-foot-by-10-foot disposal device
has an effective disposal infiltration area of 80 square feet. When used in
trenches with one foot of stone along the 4-foot sidewalls, each
4-foot-by-10-foot disposal device has an effective disposal infiltration area
of 93 square feet. When used in trenches with one foot of stone along the
10-foot sidewalls, each 4-foot-by-10-foot disposal device has an effective
disposal infiltration area of 113 square feet. A separation distance of 3 feet
from edge of stone to edge of stone is required when used in trench
configuration.
W.
PLASTIC DISPOSAL DEVICES
1.
Manufacturers: Manufacturers must be approved by the Department.
2. Configuration: These devices may be
installed in trench or cluster configuration. A 3-foot horizontal spacing must
be maintained between trenches. This spacing is in addition to any coarse
material used adjacent to the devices.
3. Sizing: These devices have an effective
disposal infiltration area in square feet per linear foot as specified in Table
7B.
TABLE 7B
Sizing for "Bio-Diffuser", "Infiltrator",
"EnviroChamber", and "Contactor" proprietary disposal devices
Device
|
Model
|
Height
|
Configuration
|
|
|
|
Cluster
|
Trench
|
Bio-Diffuser
|
Standard
|
11 inches
|
36 square feet/unit
|
44 square feet/unit [a]
|
Bio Diffuser
|
High Capacity
|
16 inches
|
36 square feet/unit [b]
|
50 square feet/unit [c,d]
|
Bio-Diffuser
|
Bio 2
|
12 inches
|
28.8 square feet/unit [b]
|
28.8 square feet/unit [c,d]
|
Bio-Diffuser
|
Bio 3
|
12 inches
|
26.4 square feet/unit
|
43.2 square feet/unit
|
Bio-Diffuser
|
Bio 2
|
12 inches
|
28.8 square feet/unit [b]
|
28.8 square feet/unit [c,d]
|
Bio-Diffuser
|
ARC 18
|
12 inches
|
2.5 square feet/linear foot [b]
|
4.0 square feet/linea r foot [c,d]
|
Bio-Diffuser
|
ARC 24
|
12 inches
|
3.7 square feet/linear foot
|
6.0 square feet/linea r foot
|
Bio-Diffuser
|
ARC 36 Standard
|
12 inches
|
5.8 square feet/linear foot
|
7.0 square feet/linea r foot
|
Bio-Diffuser
|
ARC 36 High Capacity (HC)
|
16 inches
|
5.8 square feet/linear foot
|
8.0 square feet/linea r foot
|
Infiltrator
|
EQ 24
|
11 inches
|
33.3 square feet/unit [b]
|
33.3 square feet/unit [c,d]
|
Infiltrator
|
Quick4 EQ 24
|
11 inches
|
16.0 square feet/unit
|
16.0 square feet/unit [c,d]
|
Infiltrator
|
Quick4 EQ 24 LP
|
8 inches
|
10.8 square feet/unit
|
14 square feet/unit [c,d]
|
Infiltrator
|
Quick4 EQ 36
|
12 inches
|
14.8 square feet/unit
|
20.8 square feet/unit
|
Infiltrator
|
Standard
|
12 inches
|
36 square feet/unit
|
44 square feet/unit [a]
|
Infiltrator
|
Quick4 Standard
|
12 inches
|
23.2 square feet/unit
|
28 square feet/unit [a]
|
Infiltrator
|
High Capacity
|
16 inches
|
36 square feet/unit
|
50 square feet/unit [a]
|
Infiltrator
|
Quick4 High Capacity
|
16 inches
|
23.2 square feet/unit
|
32 square feet/unit [a]
|
Contactor
|
EZ-24
|
12 inches
|
16.5 square feet/unit
|
6.21 square feet/linea r foot
|
Contactor 75
|
Contactor "C"
|
12 inches
|
36 square feet/unit
|
44 square feet/unit [e]
|
Contactor 100
|
100
|
12 inches
|
48 square feet/unit
|
57 square feet/unit
|
Contactor 125
|
125
|
18 inches
|
36 square feet/unit
|
50 square feet/unit [e]
|
Contactor
|
Recharger 180
|
20 inches
|
44 square feet/unit
|
63 square feet/unit
|
Contactor 375
|
Tripdrain
|
30 inches
|
64 square feet/unit
|
90 square feet/unit [e]
|
Contactor
|
Recharger 330
|
30 inches
|
65.25 square feet/unit
|
98.25 square feet/unit
|
Contactor
|
Recharger 400
|
32 inches
|
29 square feet/unit
|
57.6 square feet/linea r foot
|
Contactor
|
Field Drain C1-C4
|
8 inches
|
57.8 square feet/unit
|
N/A
|
Infiltrator Quick 4 Plus
[f]
|
Without End Cap,
Trench
|
Without End Cap,
Cluster
|
|
|
Quick4 Plus High Capacity
|
8.0 square feet/linear foot
|
5.8 square feet/linear foot
|
|
|
Quick 4 Plus Standard
|
7.0 square feet/linear foot
|
5.8 square feet/linear foot
|
|
|
Quick 4 Plus Standard LP
|
7.0 square feet/linear foot
|
5.8 square feet/linear foot
|
|
|
Quick 4 Plus Equalizer 36 LP
|
5.2 square feet/linear foot
|
3.7 square feet/linear foot
|
|
|
Quick 4 Equalizer 24 LP
|
3.5 square feet/linear foot
|
2.7 square feet/linear foot
|
|
|
[a] 36 inches
from edge to edge (stone to stone, if stone is used).
[b] 12 inches from edge to edge on level
systems (see manufacturer's installation guide).
[c] 18 inches, edge-to-edge, for single row
trenches.
[d] 6 inches, edge to
edge in 2 rows per trench with 36 inches between trenches.
[e] 6 feet from center to center, in trench
configuration.
[f] Infiltrator
Quick 4 notes:
1. Quick4 Plus All-in-One 12
Endcap installed at end of chamber row - 7.3 square feet/end cap or 14.6 square
feet/pair of end caps.
2. Quick4
Plus All-in-One 12 Endcap installed midline in chamber row - 4.2 square
feet/end cap.
3. Quick4 Plus
All-in-One 8 Endcap installed at end of chamber row - 2.9 square feet/end cap
or 5.8 square feet/pair of end caps.
4. Quick4 Plus All-in-One 8 Endcap installed
mid-line in chamber row - 2.2 square feet/end cap.
5. Quick4 Plus 8 Endcap installed at end of
chamber row - 1.0 square feet/end cap or 2.0 square feet/pair of end
caps.
6. Quick 4 Equalizer 24 LP -
2.9 square feet/pair of end caps.
X.
GRAVEL-LESS FABRIC WRAPPED DISPOSAL
TUBING
1. Manufacturers: Manufacturers
must be approved by the Department.
2. Configuration: Use of gravel-less fabric
covered disposal field tubing is restricted to trench configurations.
3. Sizing: These devices have an effective
disposal infiltration area of 5.0 square feet per linear foot.
TABLE 7C
Sizing for "GeoFlow" "Enviro-Septic" and
"Infiltrator ATL" gravel-less disposal
tubing
Device
|
Model
|
Configuration+
|
|
|
Cluster
|
Trench
|
GeoFlow
|
10 inches
|
N/A
|
5.0 square feet per linear foot
|
Enviro-Septic & Advanced Enviro-Septic
|
12 inches
|
N/A
|
5.0 square feet per linear foot
|
Infiltrator ATL System
|
12 inches
|
N/A
|
5.0 square feet per linear foot
|
Y.
GEOTEXTILE SAND FILTERS
1. Manufacturers: Manufacturers must be
approved by the Department.
2.
Configuration: A minimum of 12 inches horizontal spacing must be maintained
between all rows of geotextile sand filters.
3. Sizing: These devices have an effective
disposal infiltration area of 12 square feet per linear foot.
TABLE 7D
Sizing for "Geotextile Sand Filter"
gravel-less cloth disposal system
Device
|
Model
|
Configuration
|
|
|
Cluster
[b]
|
Trench[a]
|
GSF
|
Type A
|
24 square feet/ unit
|
24 square feet/unit
|
GSF
|
Type B
|
48 square feet/unit
|
48 square feet/unit
|
[a] 4 feet and
6 feet, center to center, type A units and type B units,
respectively.
[b] A minimum of 12
inches of spacing between rows of GSF units for systems that have all the rows
at the same elevation. Cluster installations that have rows that step down
slopes of 15 percent or less shall have a minimum pacing of 12 inches between
adjacent rows. Step down clustered installations on slopes of greater than 15
percent to 20 percent shall have a minimum spacing of 24 inches between
adjacent rows.
Z.
SYNTHETIC AGGREGATE CYLINDERS
1. Manufacturers: Manufacturers must be
approved by the Department.
2.
Sizing: These devices have an effective disposal infiltration area which varies
as shown in Table 7E.
TABLE 7E
Sizing for Synthetic Aggregate Cylinders
EZflow Model
|
Height
|
Configuration
|
|
|
Cluster
|
Trench
|
803H/ 803H GEO
|
8 inches
|
3.25 square feet per linear foot
|
4.0 square feet per linear foot
|
904H/ 904H GEO
|
9 inches
|
4.9 square feet per linear foot
|
6.0 square feet per linear foot
|
1201P/1201P GEO
|
12 inches
|
N/A
|
4.0 square feet per linear foot
|
1202H/1202H GEO
|
12 inches
|
5.36 square feet per linear foot
|
6.0 square feet per linear foot
|
1203H/1203H GEO
|
12 inches
|
6.4 square feet per linear foot
|
7.0 square feet per linear foot
|
AA.
PRE-TREATMENT SAND FILTERS
1. Sand filters: Pre-treatment sand filters
must be designed, installed and maintained in conformance with the guidelines
set forth in the United States Environmental Protection Agency's Design Manual
On-site Wastewater Treatment and Disposal Systems,
EPA-625/1-80-012. The specific guidance Sections are:
a. Intermittent sand filters:
EPA-625/1-80-012 Section
7(C).
b. Buried sand filters: EPA-625/1-80-012
Section 7(C).
c. Free Access sand filters
(Non-recirculating): EPA-625/1-80-012 Section
7(C).
d. Re-circulating sand filter:
EPA-625/1-80-012 Section
7(C).
BB.
SEPTIC TANK FILTERS
1. General: Septic tank outlet filters
perform two primary functions; retention of the solids in the tank and
reduction of the BOD5. A potential purchaser is advised to obtain information
pertaining to the recommended model, relative cost, availability, installation
and maintenance procedures and flow rates from the manufacturer or
distributor.
2. Manufacturers:
Manufacturers must be approved by the Department.
CC.
MECHANICAL REMEDIATION
1. Terralift and Terralift 2000. Terralift is
a pneumatic device designed to restore onsite sewage disposal systems and
improve systems of less than optimal performance, by creating a fractured soil
condition adjacent to the disposal area into which effluent can drain, as well
as fracturing the disposal area's bio-mat. Terralift is acceptable for use in
the State of Maine on a conditional basis, provided that it is operated in
conformance with stringent conditions relating to protection of ground and
surface water supplies. The Department maintains a copy of these
conditions.
DD.
POST-SEPTIC TANK EFFLUENT FILTERS
1. FRICKle Filter: A multiple chamber,
gravity flow filter device using anaerobic and aerobic processes as effluent
flows through a serpentine series of baffles. Use of a FRICKle Filter in a
replacement system is allowed a 20 percent reduction to the base design flow.
Use of a FRICKle Filter in a first-time system may be assessed 10 points toward
a First-Time System Variance, in accordance with Table 14K.
http://albertfrick.com/.
2. Norweco Bio-kinetic BK-2000: The Norweco
Bio-Kinetic Wastewater Management System BK 2000 (BK 2000) is a self-contained
plate filter installed between a treatment tank and the point of final effluent
disposal. The BK 2000 is allowed 20 points toward a First Time System Variance
in accordance with Table 14K.
http://www.norweco.com.
3. Puraflo Peat Biofilter: This product
consists of manufactured, prepackaged peat filtration and treatment system
modules. Installation of manufactured peat filtration modules do not require
prior review and approval by the Department under Section
11(D)(4). First time
system variance points may be claimed for use of the product in accordance with
Table 14K.
http://www.boradnamona.com.
4. Presby De-Nyte: The Presby De-Nyte
consists of a molded plastic cell, with corrugations along the bottom and two
sides. The cells are filled with a mixture of organic materials and mineral
aggregates, and vented according to the manufacturer's directions. The Presby
De-Nyte is designed for use with Presby Enviro-Septic systems exclusively.
First time system variance points may be claimed for use of the product in
accordance with Table 14K.
http://www.presbyenvironmental.com
EE.
UNDER-DRAINED PEAT
FILTERS
1. Scope: Under-drained peat
filters are designed to pre-treat septic tank effluent prior to its ultimate
disposal in any disposal field authorized under this rule.
2. Polyethylene liner: The under-drained peat
filter is placed in an excavation or fill material that is lined with an 18-ml
polyethylene sheeting or equivalent.
3. Final disposal in a disposal field: The
effluent from the peat filter is conveyed to a separate disposal field for
final disposal.
4. Sizing the
disposal field: The disposal field used for final disposal is sized according
to Sections
5(E) and
5(F) and sized at 90%
of the minimum hydraulic loading rate required in Table 5D. Field size may be
further reduced based on Table 5B.
FF.
SUBSTITUTION OF PROPRIETARY
DEVICES
1. Any substitution of a
proprietary device must be approved by the site evaluator.
2. The following proprietary devices may be
substituted for one another without revisions to the permitted HHE-200 Form,
unless specifically prohibited by notation of the licensed site evaluator. The
bottom elevation(s) specified on the original HHE-200 form must be utilized
with the substituted devices.
a. Concrete
chambers: Any approved manufacturer's 4-foot-by-8-foot or 8-foot-by-8-foot
chamber may be substituted for another approved manufacturer's 4-foot-by-8-foot
or 8-foot-by-8-foot chamber, provided the original disposal area configuration
is maintained.
b. Plastic chambers
and other devices: Substitution of one approved device for another is permitted
as noted in Table 7H. When the trench configuration is utilized, the number of
trenches specified for the original design must be maintained with the
substituted devices. When a device of a different length than the originally
specified device is substituted, the minimum square footage specified on the
original HHE-200 Form governs.
GG.
DRIP IRRIGATION DISPOSAL
1. A drip irrigation disposal system receives
effluent from a treatment tank and dispenses it to an infiltration system that
is installed at a shallow depth in native or fill soil. The Department may
require a layer of soil, mulch, or other engineered fill cover on the surface
of the native soil, depending on wastewater quality delivered to the drip
emitters.
2. All drip irrigation
systems must be designed to prevent effluent ponding on the soil
surface.
3. Application:
Applications for drip irrigation systems must include the following provisions:
a. Advanced Treatment: Documentation the
advanced treatment method proposed achieves the effluent criteria specified in
Tables 7F and 7G, such as the type of advanced treatment system and the
manufacturer's warranty;
b. Design
Calculations: Design calculations, showing conformance with provisions of this
rule; and
c. Application (HHE-200
Form): An application completed in conformance with this rule by a licensed
site evaluator.
4. Drip
irrigation disposal systems must be sized as follows:
a. Porous Hose System: A drip irrigation
system utilizing porous hose must be sized pursuant to the specific product's
approval granted by the Department.
b. Drip Emitter System: A drip irrigation
system utilizing manufactured drip emitters must be sized pursuant to the
manufacturer's recommendations, as approved by the Department.
5. Drip irrigation systems must be
installed in conformance with the following criteria:
a. Separation from limiting factor: All drip
irrigation lines must be installed at least 12 inches above the groundwater
table or 24 inches above bedrock, whichever is more limiting. Backfill or mulch
must be placed over the top of the porous hose in sufficient quantity and
depth, as specified by the system supplier to prevent surface ponding of
effluent.
b. Separation from site
features: All drip irrigation systems must be installed in conformance with
horizontal setback requirements of this rule.
c. Line spacing: Drip irrigation lines must
be placed at least 12 inches apart, unless variations in spacing allow
preservation of existing trees and shrubs or enhance performance to overcome
site limitations. The site evaluator shall note such variations on the
application.
d. Protection from
freezing: Year-round drip irrigation systems must be installed with a minimum
of 12 inches of suitable cover material to prevent freezing of the disposal
area.
Table 7F
Minimum Porous Hose Effluent Quality
Total Suspended Solids
|
10 milligrams per liter, 30-day arithmetic
mean
|
Five Day Biochemical Oxygen Demand
|
10 milligrams per liter, 30-day arithmetic
mean
|
Total nitrogen
|
53 milligrams per liter, five-month arithmetic
mean
|
Total coliform
|
10 (Log 10) colony forming units per 100
milliliters
|
Table 7G Minimum Drip Emitter Effluent
Quality
Total Suspended Solids
|
30 milligrams per liter, 30-day arithmetic
mean
|
Five Day Biochemical Oxygen Demand
|
30 milligrams per liter, 30-day arithmetic
mean
|
Total nitrogen
|
53 milligrams per liter, five-month arithmetic
mean
|
Total coliform
|
100 (Log10) colony forming units per 100
milliliters
|
HH.
NEW PRODUCT REGISTRATION
1. General: Any manufacturer or distributor
submitting new products (including, but not limited to, remedial products,
processes or devices, disposal system components, pre-filters or proprietary
disposal devices) to the Department for code approval and registration must
demonstrate that the conditions set forth in this Section are met.
Certification to certain national or international standards such as ANSI/NSF
40 (Residential Wastewater Treatment Systems), ANSI/NSF 46 (Wastewater
Components and Devices), or relevant standards from the Canadian Standards
Association (CSA) may be accepted as verification that the conditions set forth
in this Section are met. The Department will maintain an updated list of
subsurface wastewater related products approved for use in Maine.
2. Meets the intent of this rule: The product
is designed to protect public health, prevent the creation of any nuisance, and
prevent environmental pollution to the same extent as comparable products
presently authorized by the Department for use this rule;
3. Sound engineering principles: The product
is based on sound engineering principles and can be expected to provide the
same level of protection to public health and the environment as offered by the
authorized products presently authorized by the Department for use in this
rule. Sound engineering principles may be demonstrated by submitting a letter
to the Department from a) a certifying organization, such as the Building
Officials and Code Administrators (BOCA), or other suitable organization
stating their approval of the product, or b) the American Society for Testing
and Materials (ASTM) indicating the subject product (used as indicated in the
request) meets the ASTM standard as specifically listed in the appropriate
section of any nationally recognized code, such as BOCA or equal.
4. Registration: There are levels of approval
for product registration: Pilot, Provisional, and General Use. All Pilot and
Provisional product registration installations must be approved by the
Department prior to installation.
a. Pilot
approval: Pilot approval allows an applicant to demonstrate the general ability
of a proposed product to treat wastewater as defined in the Rules, or perform
other functions as claimed by the applicant. No less than 10 installations of a
specific product registration must be granted Pilot approval by the Department.
Pilot approvals must be limited to sites which do not otherwise require any
variance or waiver to the Rules, if wastewater treatment is claimed by the
applicant. If wastewater treatment is claimed by the applicant, on no less than
a bi-weekly basis for a period of not less than six months, and once per month
for at least an additional six months, the applicant shall test the influent
and effluent of each installed product registration for the following
parameters: five day Biochemical Oxygen Demand (BOD5), Total Suspended Solids
(TSS), Nitrate Nitrogen (N03), Nitrite Nitrogen (NO2), Total Kjeldahl Nitrogen
(TKN), Ammonia Nitrogen (NH4), and coliform bacteria. The results of these
tests must be submitted to the Department on no less than a quarterly basis.
Historic data from other jurisdictions may be submitted, if available. If such
data are satisfactory, the applicant may bypass Pilot approval and proceed to
Provisional status.
b. Provisional
approval: Provisional approval allows an applicant to demonstrate ability of a
proposed product to operate under a broader range of site conditions and to
provide a larger number of data sources for such demonstration. No less than 50
installations of a specific new or experimental technology specific product
registration must be granted Provisional system approval by the Department, of
which 10 may be Pilot systems previously approved by the Department.
Provisional product registrations must not be granted until the Pilot
installations have been in operation for at least one year, or if historic data
is accepted by the Department. Provisional product registration installations
may include sites which require a variance or waiver to the Rules, with the
provision that such variance or waivers are also subject to the standard
variance requirements of the Rules, i.e., a passing point score for soils
related variance, etc. If wastewater treatment is claimed by the applicant, on
no less than a monthly basis for a period of not less than one year, the
applicant shall test the influent and effluent of each installed provisionally
approved product for the following parameters: five-day Biochemical Oxygen
Demand (BOD5), Total Suspended Solids (TSS), Nitrate Nitrogen (N03), and
coliform bacteria. The results of these tests must be submitted to the
Department on no less than a semiannual basis. Existing data from other
jurisdictions may be submitted, if available. If such data are satisfactory,
the applicant may bypass Provisional approval and proceed to General Use
status.
c. General Use: To receive
General Use approval for a product registration, the applicant shall
demonstrate that the 50 installations allowed under Provisional approval have
operated as designed and intended. Upon such demonstration, the provisionally
approved product under consideration must be granted written General Use status
approval for use in Maine and may be used immediately as provided in the
written General Use status approval. All products that receive written General
Use status approval, will be added to the Department's List of Approved
Products, available at
https://www.maine.gov/dhhs/mecdc/environmental-health/plumb/lists.htm.
d. Advanced Wastewater Treatment Units and
Effluent Filters: Advanced treatment units for treatment of wastewater as
defined in this rule, and septic tank effluent filters which have been
certified by the National Sanitation Foundation (NSF), Canadian Standards
Authority (CSA), or other third party testing entity are accepted by the
Department for General Use in Maine, upon submission of such certification to
the Department.
e. Other Criteria:
The Department may consider other relevant supporting data for product
registrations on a case-by-case basis.
f. Failure to perform: In the event that a
product fails to perform as claimed by the applicant, the Department will
contact the manufacturer to discuss the issue and potential solutions to the
product failure. If a solution is not possible, based on these discussions,
then the Department may prohibit use of the product in Maine, including all
installations pursuant to this Section. Use of the product must not resume
until the applicant and the Department reach a mutually acceptable agreement
for resolving the failure to perform as claimed.
TABLE 7H
PLUMBING MATERIAL STANDARDS FOR DISPOSAL
SYSTEMS
ASTM NUMBER FOR PLASTIC PIPE MUST BE LATEST EDITION
AS LISTED IN ANNUAL BOOK OF ASTM STANDARDS, PART 34
NOTES:
(A) PLASTIC PIPE MUST BE SLEEVED WHEN PASSING THROUGH
MASONRY
(B) PERFORATED PIPE MUST BE USED WITHIN THE ACTUAL
DISPOSAL FIELD
(C) WATER AND SEWER PIPE LESS THAN 10 FEET (CENTER TO
CENTER) OR WATER AND SEWER PIPE IN THE SAME TRENCH REQUIRES THE WATER PIPE TO
BE ON A SHELF AT LEAST 18 INCHES ABOVE AND 24 INCHES (CENTER TO CENTER) APART
FROM EACH OTHER (HORIZONTAL MEASURE)
X = PERMISSIBLE |
x
|
x
|
x
|
x
|
x
|
ABS (ASTM D1527) Sch. 40, 80
|
x
|
|
x
|
|
|
ABS (ASTM D2282) SDR 13.5, 17, 21, 26
|
|
x
|
x
|
x
|
x
|
ABS (ASTM D2661) DWV Sch. 40
|
|
x
|
x
|
|
x
|
ABS (ASTM D2751, F810) Sewer Grade
|
|
|
|
x
|
x
|
Cast Iron
|
|
|
|
|
x
|
Concrete (ASTM C75, C200)
|
x
|
|
x
|
|
x
|
PB (ASTM D2662) Pipe SDR 7, 9, 11.5, 15
|
x
|
x
|
x
|
|
|
PE (ASTM D1248) Straight Wall
|
x
|
|
x
|
|
x
|
PE (ASTM D2239) Pipe SDR 5.3, 7,9, 11.5, 15,
19
|
x
|
|
x
|
|
x
|
PE (ASTM D2737) Tubing SDR 7.3, 9, 11
|
|
x
|
x
|
|
|
PE (ASTM 3350) Smooth Wall Pipe, SDR 38, 35
|
x
|
x
|
x
|
x
|
x
|
PVC (ASTM D1785) Sch. 40, 80, 120
|
x
|
|
x
|
|
x
|
PVC (ASTM D2241) SDR 13.5, 17, 21, 26, 32.5,
41,64
|
|
x
|
x
|
x
|
x
|
PVC (ASTM D2665) DWV Sch. 40
|
|
|
x
|
|
|
PVC (ASTM D2629; F810) Thin Walled Perforated,
Disposal Field Only
|
|
x
|
x
|
x
|
x
|
PVC (ASTM D3034) SDR 23.5, 26, 35, 41
|
PRESSURE SEWER (OR PRESSURE LINE FROM PUMP CHAMBER
TO DISPOSAL AREA)
EFFLUENT PIPE (LINE FROM TREATMENT TANK TO DISPOSAL
FIELD FOOTPRINT)
DISTRIBUTION PIPE (PIPING WITHIN THE DISPOSAL FIELD
FOOTPRINT) (SEE B)
BUILDING SEWER (WATER SERVICE IN SAME TRENCH) (SEE
C)
BUILDING SEWER (SEPARATE FROM WATER SERVICE)
BUILDING SEWER (SEPARATE FROM WATER SERVICE)
|
Table 7I
FRICTION LOSS IN SCHEDULE 40 PLASTIC PIPE
FEET
OF HEAD LOSS PER 100 FEET OF PIPE
Flow
|
Pipe diameter in
inches
|
|
11/2 Inch
|
2 Inch
|
3 Inch
|
3 gpm
|
0.07 feet
|
|
|
4 gpm
|
0.12 feet
|
|
|
5 gpm
|
0.18 feet
|
|
|
6 gpm
|
0.25 feet
|
0.07 feet
|
|
7 gpm
|
0.36 feet
|
0.10 feet
|
|
8 gpm
|
0.46 feet
|
0.14 feet
|
|
9 gpm
|
0.58 feet
|
0.17 feet
|
|
10 gpm
|
0.70 ft
|
0.21 feet
|
|
11 gpm
|
0.84 feet
|
0.25 feet
|
|
12 gpm
|
1.01 feet
|
0.30 feet
|
|
13 gpm
|
1.17 feet
|
0.35 feet
|
|
14 gpm
|
1.33 feet
|
0.39 feet
|
|
15 gpm
|
1.45 feet
|
0.44 feet
|
0.07 feet
|
16 gpm
|
1.65 feet
|
0.50 feet
|
0.08 feet
|
17 gpm
|
1.86 feet
|
0.56 feet
|
0.09 feet
|
18 gpm
|
2.07 feet
|
0.62 feet
|
0.10 feet
|
19 gpm
|
2.28 feet
|
0.68 feet
|
0.11 feet
|
20 gpm
|
2.46 feet
|
0.74 feet
|
0.12 feet
|
25 gpm
|
3.75 feet
|
1.10 feet
|
0.16 feet
|
30 gpm
|
5.22 feet
|
1.54 feet
|
0.23 feet
|
35 gpm
|
|
2.05 feet
|
0.30 feet
|
40 gpm
|
|
2.62 fee
|
0.39 feet
|
45 gpm
|
|
3.27 feet
|
0.48 feet
|
50 gpm
|
|
3.98 feet
|
0.58 feet
|
TABLE 7J
HOLDING CAPACITY OF PIPES
Diameter
|
Pipe Volume
|
|
Inches
|
Gallons/Foot
|
Length/Gallon
|
1 1/4
|
0.0776
|
12 feet 10 5/8 inches
|
1 1/2
|
0.1057
|
9 feet 5 1/2 inches
|
2
|
0.1632
|
6 feet 1 1/2 inches
|
2 1/2
|
0.2549
|
3 feet 11 3/4 inches
|
3
|
0.3672
|
2 feet 8 3/4 inches
|
4
|
0.6528
|
1 foot 6 inches
|
5
|
1.0199
|
1 foot 0 inches
|
6
|
1.469
|
8 inches
|
7
|
1.999
|
6 inches
|
8
|
2.611
|
4 1/2 inches
|
1 gallon of water = 8.35 pounds
1 cubic foot of water = 7.48 gallons