801.1 Pump type and size: Size and install pump to at least the minimum of the Manufacturer's recommendations.
801.2 Check valves: One (1) check valve shall be installed within 20 feet of the discharge of the pump. All check valves shall be accessible for service but shall not be direct buried.
801.3 Disinfection: For any new installation of a submersible pump or servicing of wire, pipe and/or pump repair within the well, the well shall be chlorinated to a minimum concentration of 50 parts per million for a minimum of 24 hours upon completion of installation or repair.
Disclaimer: These regulations may not be the most recent version. Maine may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.