A.
Applicability
(1) This section
applies to the establishment of vegetation adjacent to any protected natural
resource and the installation of riprap along the shoreline of a great pond,
freshwater wetland with over 20,000 square feet of open water, stream or
brook.
(2) This section applies
only to areas where erosion exists and vegetation is not present, as
demonstrated by photographs submitted with the notification form.
(3) This section does not apply to riprap on
any river as defined by 38 M.R.S.A. Section
436- A(11), the Mandatory Shoreland
Zoning Act (information is available at the Town Office).
(4) This section does not apply to a riprap
project that affects more than 100 feet of shoreline.
(5) This section does not apply to areas
within any portion of a coastal sand dune system even if portions of these
systems extend into the coastal wetland.
(6) This section does not apply to an
activity that will not conform to the local shoreland zoning
ordinance.
NOTES:
(1) Contact
the local Code Enforcement Officer for information on local shoreland zoning
requirements.
(2) A permit will be
required from the US Army Corps of Engineers for riprap projects that include
fill below the ordinary high water line of fresh waters or below the spring
high tide line of tidal waters.
A copy of the PBR notification form and original photographs,
not photocopies, should be submitted to the Corps of Engineers for these
activities (US Army Corps of Engineers, 675 Western Avenue, Suite #3,
Manchester, ME 04351. Tel. (207) 623-8367).
B.
Submissions
(1) The applicant is required to submit
photographs of the entire shoreline area where this activity is
proposed.
(2) Photographs showing
the finished activity must be submitted within 20 days of the activity's
completion. The photographs must be sent with a copy of the notification form
or labeled with the applicant's name and the town in which the activity took
place.
(3) A scaled drawing,
including a cross section, of the proposed riprap installation. The drawing
must clearly depict the extent of riprap proposed to be installed, such as the
length along shore and height above the normal high water line.
It is not necessary to have the plan professionally prepared.
However, it must be legible and drawn to a scale that provides a clear
representation of distances and measurements on the plan.
(4) Professional design plans for riprap on
streams and brooks when required pursuant to paragraph C(12) of this
section.
C.
Standards
(1) Riprap may be
utilized only where eroded slopes exceed 3 horizontal feet to 1 vertical foot
(approximately 33% slope), or where riprap is used to stabilize an existing
stormwater outfall. Where eroded slopes are shallower than 3 horizontal to 1
vertical, vegetation must be used to control erosion.
(2) Riprap installed on the shoreline of a
great pond or open water wetland may not extend higher than 2 feet above the
normal high water line. Riprap installed on a river, stream or brook may not
extend higher than 2 feet above the normal high water line, or to the elevation
of the 100-year flood where mapped by the Federal Emergency Management Agency,
whichever is higher.
(3) The
following measures must be taken to prevent erosion of soil or fill material
from disturbed areas into the resource:
(a)
Staked hay bales or silt fence must be properly installed between the area of
soil disturbance and the resource before the activity begins;
(b) Hay bales or silt fence barriers must be
maintained until the disturbed area is permanently stabilized;
(c) Within 7 calendar days following the
completion of any soil disturbance, and prior to any storm event, mulch must be
spread on any exposed soils;
(d)
All disturbed soils must be permanently stabilized; and
(e) Within 30 days of final stabilization of
the site, any silt fence must be removed.
NOTE: For guidance on erosion and sedimentation controls,
consult the Maine Erosion and Sediment Control BMPs, dated March 2003. This
handbook and other references are available from the DEP.
(4) New soil may be brought to the
site and soil amendments, such as fertilizer or lime, may be used to increase
soil fertility provided:
(a) Slopes do not
exceed 3 horizontal to 1 vertical;
(b) Existing vegetation is not permanently
removed;
(c) Water bars or
diversions are used to divert stormwater runoff away from the loam;
(d) Depth of new soil is less than 2
inches;
(e) The amendment is worked
into the underlying soils;
(f)
Disturbed areas are immediately mulched and seeded; and
(g) Final vegetation consists of native trees
and shrubs, or matches existing vegetation immediately adjacent to the treated
area.
(5) Rocks used for
riprap may not be obtained from the shoreline (because they help prevent
erosion) or below the normal high water line (because they provide habitat for
aquatic life).
NOTE: On many slopes, slumping is caused by wave or water
motion undercutting the bank. If riprap is placed only at the bottom of the
slope, and the upper portions of the bank are graded and revegetated, the cost
of the shoreline stabilization project can be reduced.
(6) The slope of the riprap may not be
steeper than 1 horizontal to 1 vertical, nor shallower than 3 horizontal to 1
vertical.
(7) Riprap must be
anchored at the base of the existing bank by placing the bottom row of rock in
a trench excavated at least to a depth equal to the height of the largest rock,
or the riprap must be pinned to underlying ledge.
(8) A layer of filter fabric and crushed
stone must be placed under the riprap to prevent the washing of soil particles
into the water.
(9) No fill
material other than the riprap and crushed stone may be placed below the normal
high water line.
(10) Riprap may
not be placed in front of a retaining wall such that it extends further into
the water.
(11) A buffer strip of
undisturbed vegetation at least 25 feet wide must be established and maintained
along the upland edge of any riprap placed for the protection of agricultural
land.
(12) Design of riprap on
stream or brook banks must be approved by either a Maine Registered
Professional Engineer, the United States Natural Resources Conservation
Service, or the local Soil and Water Conservation District. Evidence of this
approval or plans stamped by a professional engineer must be submitted along
with the Notification Form. With prior written agreement, the DEP may waive
this standard for minor riprap activities on small streams.
(13) When riprap is necessary along a river,
stream or brook, it must be combined with tree and shrub plantings to provide
bank stabilization, shading of the water and cover for wildlife.
(14) If work is performed in a river, stream
or brook that is less than three feet deep at the time of the activity and at
the location of the activity, the applicant must provide for temporary
diversion of flow to the opposite side of the channel while work is in
progress.
(a) Diversion may be accomplished by
placing sandbags, timbers, sheet steel, concrete blocks, 6+ mil polyethylene or
geotextiles from the bank to midstream on the upstream side of the activity. No
more than two-thirds (2/3) or 25 feet of stream width, whichever is less, may
be diverted at one time.
(b) Any
material used to divert water flow must be completely removed upon completion
of the activity, and the stream substrate must be restored to its original
condition.
(c) A pump may be
operated, where necessary, for a temporary diversion. The pump outlet shall be
located and operated such that erosion or the discharge of sediment to the
water is prevented.
(15)
Wheeled or tracked equipment may not operate in the water. Equipment operating
on the shore may reach into the water with a bucket or similar extension.
Equipment may cross streams on rock, gravel or ledge bottom.
(16) Work below the high water line of agreat
pond, river, stream or brook must be done at low water except as required for
emergency flood control work.
(17)
All excavated material must be stockpiled either outside the protected natural
resource or on mats or platforms. Hay bales or silt fence must be used, where
necessary, to prevent sedimentation. All excavated material must be removed to
a location more than 75 feet from the protected natural resource, unless
otherwise approved by the DEP, and properly stabilized with vegetation upon
project completion.
(18)
Disturbance of vegetation must be avoided if possible. If vegetation must be
disturbed during the activity, similar types and amounts of vegetation must be
re-established immediately upon completion of the activity and must be
maintained.
(19) Non-native species
may not be planted in disturbed areas.
(20) Riprap projects must be constructed in
accordance with the plans or drawings submitted pursuant to subsections B(3)
and (4) of this section, as applicable.
D.
Definitions. The following
terms, as used in this chapter, have the following meanings, unless the context
indicates otherwise:
(1)
Fill.
a. (verb) To put into or upon, supply to, or
allow to enter a water body or wetland any earth, rock, gravel, sand, silt,
clay, peat, or debris;
b. (noun)
Material, other than structures, placed in or adjacent to a water body or
wetland.
(2)
Riprap. Heavy, irregularly-shaped rocks that are fit into place,
without mortar, on a slope. Square or rectangular rocks with flat faces, such
as quarry stone or manufactured blocks, do not qualify as
"irregularly-shaped".
(3)
Structure. Anything built for the support, shelter or enclosure of
persons, animals, goods or property of any kind, together with anything
constructed or erected with a fixed location on or in the ground. Examples of
structures include buildings, utility lines and
roads.