Current through 2024-38, September 18, 2024
A.
Applicability
(1) This section
applies to the restoration of an altered portion of a coastal wetland,
freshwater wetland, great pond, river, stream or brook to its pre-existing
natural condition through the removal of fill, structures or debris which is
located in, on over, or adjacent to the natural resource.
(2) This section applies to the removal of
non-native species and the planting of natural vegetation in any protected
resource.
(3) This section applies
to the retrieval of sand from below the normal high water line for
redistribution on an existing adjacent sand beach on a great pond.
(4) This section applies to the restoration
of the natural grade within a dredged area of a freshwater or coastal
wetland.
(5) This section does not
apply to:
(a) Restoration or replacement of a
structure or unnatural condition such as the installation of a dam
structure;
(b) Conversion of
existing natural wetlands to wetland of a different type through flooding,
inundation or other means;
(c)
Dredging of silt, sand or soil materials which have been naturally deposited
from a great pond, river, stream or brook, coastal wetland or freshwater
wetland except that eroded sand may be retrieved from a great pond for
redistribution on an existing adjacent sand beach;
(d) Mining of gravel or other mineral
materials from a river, stream, or brook;
(e) Replacement of eroded soil material in
areas above, below and adjacent to the normal high water mark of a great pond,
river, stream or brook, freshwater wetland, or coastal wetland, except that
sand may be regraded on an existing sand beach;
(f) Removal of a man-made dam
structure;
(g) Draining of a
freshwater wetland to convert an area to upland; or
(h) An activity occurring within a coastal
sand dune system.
(6)
This section does not apply to an activity that is not or will not be in
compliance with the terms and conditions of permits issued under the Site
Location of Development Law, 38°M.R.S.A. Sections
481 to
490, the Storm Water Management Law,
38 M.R.S.A. Section
420- D, or the Natural Resources
Protection Act, 38 M.R.S.A. Sections
480-A to
480- Z.
(7) This section does not apply to an
activity that will not conform to the local shoreland zoning
ordinance.
NOTE:
(1) Contact
the local Code Enforcement Officer for information on local shoreland zoning
requirements.
(2) A permit will be
required from the US Army Corps of Engineers for the following types of
projects:
(a) Any activity involving impacts
(direct and secondary) to freshwater wetlands;
(b) Any activity within a coastal
wetland;
(c) Any activity within an
open water area;
(d) Any activity
within a river, stream or brook between October 2 and July 14; or
(e) Any activity involving work in waterways
designated as Essential Fish Habitat for Atlantic salmon including all aquatic
habitats in the watersheds of the following rivers and streams, including all
tributaries to the extent that they are currently or were historically
accessible for salmon migration: St. Croix, Boyden, Dennys, Hobart Stream,
Aroostook, East Machias, Machias, Pleasant, Narraguagus, Tunk Stream, Patten
Stream, Orland, Penobscot, Passagassawaukeag, Union, Ducktrap, Sheepscot,
Kennebec, Androscoggin, Presumpscot, and Saco River.
A copy of the PBR notification form and original photographs,
not photocopies, should be submitted to the Corps of Engineers for these
activities (US Army Corps of Engineers, 675 Western Avenue, Suite #3,
Manchester, ME 04351. Tel. (207) 623-8367).
B.
Submissions
(1) The applicant is
required to submit photographs of the area in which this activity is
proposed.
(2) Photographs showing
the finished activity must be submitted within 20 days of the activity's
completion. The photographs must be sent with a copy of the notification form
or labeled with the applicant's name and the town in which the activity took
place.
(3) For an activity
occurring in tidal waters, notice of approval of timing from the Department of
Marine Resources must be submitted to the DEP with the notification
form.
C.
Standards
(1) The following
measures must be taken to prevent erosion of soil or fill material from
disturbed areas into the proposed resource:
(a) Staked hay bales or silt fence must be
properly installed between the area of soil disturbance and the resource before
the activity begins;
(b) Hay bales
or silt fence barriers must be maintained until the disturbed area is
permanently stabilized;
(c) Within
7 calendar days following the completion of any soil disturbance, and prior to
any storm event, mulch must be spread on any exposed soils;
(d) All disturbed soils must be permanently
stabilized; and
(e) Within 30 days
of final stabilization of the site, any silt fence must be removed.
NOTE: For guidance on erosion and sedimentation controls,
consult the Maine Erosion and Sediment Control BMPs, dated March 2003. This
handbook and other references are available from the DEP.
(2) Disturbance of wetland
vegetation must be avoided if possible. If wetland vegetation must be disturbed
during the activity, it must be reestablished immediately upon completion of
the activity and must be maintained.
(3) Non-native wetland plants may not be
planted in disturbed areas.
(4)
Only material that has been placed in a natural resource by persons may be
removed from these waterbodies except for debris deposited within the previous
12 calendar months, and sand that will be regraded onto existing adjacent sand
beaches.
(5) Sand may be regraded
from below the normal high water line, but machinery may not operate in the
water. Equipment operating on shore may reach into the water with a bucket or
similar extension. Areas covered by vegetation, either aquatic or terrestrial,
may not be disturbed during any beach regrading.
(6) Any activity involving the regrading of
an existing sand beach must include the installation of permanent erosion
control devices, such as water bars and diversion ditches, that prevent future
erosion of the sand from upland runoff. The erosion control devices must be
installed prior to the regrading of the beach.
(7) Vegetation and soil material used in
restoring wetland areas must be similar to the vegetation and soil materials
occurring under pre-existing natural conditions.
(8) No fill other than soil material used to
restore natural elevations within a dredged area of a coastal or freshwater
wetland may be placed in or adjacent to a natural resource. Sand may not be
brought in from off-site to replenish an existing beach.
NOTE: Erosion of sand from beaches may be due to wave action
or the action of overland water flows. Contact the DEP, the local Soil and
Water Conservation District, or the local lake association for assistance with
identifying sources of beach erosion.
(9) Wheeled or tracked equipment may not
operate in the water. Equipment operating on the shore may reach into the water
with a bucket or similar extension. Equipment may cross streams on rock, gravel
or ledge bottom.
(10) All wheeled
or tracked equipment that must travel or work in a vegetated wetland area must
travel and work on mats or platforms in order to protect wetland
vegetation.
(11) All excavated
material must be stockpiled either outside the wetland or on mats or platforms.
Hay bales, silt fence or mulch must be used, where necessary, to prevent
sedimentation.
(12) If the activity
occurs within tidal waters, the activity must occur during the time period
approved by the Department of Marine Resources.
D.
Definitions. The following
terms, as used in this chapter, have the following meanings, unless the context
indicates otherwise:
(1)
Dam. Any
man-made artificial barrier, including appurtenant works, the site on which it
is located and appurtenant rights of flowage and access, that impounds or
diverts a river, stream or brook or great pond.
(2)
Dredge. To move or remove,
by digging, scooping, or suctioning any sand, silt, mud, gravel, rock, or other
material from the bottom of a water body or wetland surface.
(3)
Fill.
a. (verb) To put into or upon, supply to, or
allow to enter a water body or wetland any earth, rock, gravel, sand, silt,
clay, peat, or debris;
b. (noun)
Material, other than structures, placed in or adjacent to a wetland or water
body.
(4)
Debris. Non-mineral materials (including but not limited to wood,
brush or flotsam) deposited by wind, wave action, flooding or wild animals
within the last 12 months. This term includes beaver dams, but does not include
beaver or muskrat houses or nests of wild birds such as wading birds or
waterfowl.
(5)
Restoration. An activity returning a great pond, coastal wetland,
freshwater wetland, river, stream or brook from a disturbed or altered
condition with lesser acreage or fewer functions to a previous condition with
greater acreage or functions.
(6)
Structure. Anything built for the support, shelter or enclosure of
persons, animals, goods or property of any kind, together with anything
constructed or erected with a fixed location on or in the ground. Examples of
structures include buildings, utility lines and roads.
(7)
Non-native wetland plants.
Wetland grasses, forbs, shrubs, or trees not native to the State of Maine, for
example, common reed (Phragmites communis) and purple
loosestrife (Lythrum salicaria).