A.
Applicability
(1) This section applies to the construction
of a bridge span or culvert crossing of a river, stream or brook, and
associated accessway construction within 25 feet of the river, stream or brook
crossing excluding the following:
(a)
Crossings of outstanding river segments identified in 38 M.R.S.A. Section
480- P;
(b) Crossings of any river as defined by 38
M.R.S.A. Section
436- A(11), the Mandatory Shoreland
Zoning Act (information is available at the Town Office); or
(c) Crossings of any portion of a river,
stream or brook that experiences tidal action.
NOTE: Temporary structures do not require a permit from the
department under the Natural Resources Protection Act (NRPA) provided no
filling and minimal soil disturbance occurs. All crossings involving filling in
and adjacent to a river, stream or brook, such as culvert crossings, are
subject to the NRPA and must first receive a permit before construction.
(2) This section also
applies to the establishment of a permanent stream ford for purposes of timber
harvesting, livestock, agriculture and construction and maintenance of a
utility line.
(3) A stream crossing
constructed between July 15 and October 1 that is associated with forest
management activities is exempt from the 14 day waiting period required in
Section 1(C)(1).
(4) A stream crossing constructed between
July 15 and October 1 that is performed or supervised by individuals currently
certified in erosion control practices by the DEP is exempt from the 14 day
waiting period required in Section
1(C)(1).
(5) Multiple stream crossings may be
submitted on one PBR notification form as long as all of the crossing
activities are located within one town.
(6) This section does not apply to an
activity that is not or will not be in compliance with the terms and conditions
of permits issued under the Site Location of Development Law, 38 M.R.S.A.
Sections 481 to
490, the Storm Water Management Law,
38 M.R.S.A. Section
420- D, or the Natural Resources
Protection Act, 38 M.R.S.A. Sections
480-A to
480- Z.
(7) This section does not apply to an
activity that will not conform to the local shoreland zoning
ordinance.
NOTES:
(1) Contact
the local Code Enforcement Officer for information on local shoreland zoning
requirements.
(2) Maintenance and
repair of a public or private crossing of a river, stream or brook is exempt
from the NRPA provided that:
(a) Erosion
control measures are taken to prevent sedimentation of the water;
(b) The crossing does not block fish passage
in the water course; and
(c) Any
replaced culvert is not more than 25% longer than the culvert being replaced
and is not longer than 75 feet.
(3) A permit will be required from the US
Army Corps of Engineers for the following types of projects:
(a) Any activity involving impacts (direct
and secondary) to freshwater wetlands; or
(b) An activity within a river, stream or
brook between October 2 and July 14.
A copy of the PBR notification form and original photographs,
not photocopies, should be submitted to the Corps of Engineers for these
activities (US Army Corps of Engineers, 675 Western Avenue, Suite #3,
Manchester, ME 04351. Tel. (207) 623-8367).
B.
Submissions
(1) For any crossing
involving trenching or disturbance of substrate in a river, stream or brook
that occurs between October 2 and July 14, the proposed dates for construction
of the crossing must be clearly identified on the notification form under
"Description of Project".
(2)
Except for crossings associated with forest management activities, the
applicant is required to submit photographs of the area that will be affected
by the activity proposed.
(3)
Photographs showing the completed project and the affected area must be
submitted within 20 days of the activity's completion. The photographs must be
sent with a copy of the notification form or labeled with the applicant's name
and the town in which the activity took place.
C.
Standards
(1) The following measures must be taken to
prevent erosion of soil or fill material from disturbed areas into the
resource:
(a) Staked hay bales or silt fence
must be properly installed between the area of soil disturbance and the
resource before the activity begins;
(b) Hay bales or silt fence barriers must be
maintained until the disturbed area is permanently stabilized;
(c) Within 7 calendar days following the
completion of any soil disturbance, and prior to any storm event, mulch must be
spread on any exposed soils;
(d)
All disturbed soils must be permanently stabilized; and
(e) Within 30 days of final stabilization of
the site, any silt fence must be removed.
NOTE: For guidance on erosion and sedimentation controls,
consult the Maine Erosion and Sediment Control BMPs, dated March 2003. This
handbook and other references are available from the DEP.
(2) If a perennial watercourse to
be crossed is used for navigation, the crossing must consist of a bridge span
or pipe arch with at least 4 feet of clearance during normal high water for
boat traffic.
(3) If the stream to
be crossed is a perennial watercourse and has a slope of more than 2%, a bridge
or a pipe arch must be used to maintain the natural streambed.
(4) Fill sideslopes in a stream or floodplain
wetland must be maintained at a slope no shallower than 3 horizontal to 1
vertical and no steeper than 1.5 horizontal to 1 vertical. Fill sideslopes must
be stabilized at the completion of the activity.
NOTE: Uncompacted soils or sandy soils that are saturated at
the toe of a slope will be unstable at a 1.5 to 1 slope.
(5) A bridge or culvert must provide an
opening with a cross-sectional area at least equal to 3 times the
cross-sectional area of the stream channel or sufficient in size to accommodate
25-year frequency water flows.
NOTE: Stream crossings allowable under this section but
located in flood hazard areas (i.e. A zones) as identified on a community's
Flood Insurance Rate Maps (FIRM) or Flood Hazard Boundary Maps (FHBM) must be
designed and constructed under the stricter standards contained in that
community's National Flood Insurance Program (NFIP). For example, a crossing
may be required to pass a 100-year flood event.
(6) Road surfaces must be constructed in a
manner to prevent erosion of material into the river, stream or
brook.
(7) Surface water on or
adjacent to crossing approaches must be diverted through vegetative filter
areas at least 25 feet long to avoid sedimentation of the watercourse. Roadside
ditches may not extend to the resource being crossed.
NOTE: Surface water on or adjacent to crossing approaches
should be diverted through vegetative filter areas to avoid sedimentation of
the watercourse. Because roadside ditches may not extend to the resource being
crossed, filter areas should be established in accordance with the following
tables:
Average slope of land between exposed mineral soil
and normal high water mark (percent) | Width of strip between ditch
terminus and normal high water mark (feet along surface of the ground) |
0 | 25 |
10 | 45 |
20 | 65 |
30 | 85 |
40 | 105 |
50 | 125 |
60 | 45 |
70 | 165 |
(8) A
stream ford must be lined with crushed stone, blasted ledge, washed stone,
gabion blankets or geotextile material for erosion control when the natural
stream bed does not consist of ledge or rock.
(9) A stream ford must allow for fish passage
at all times of the year and may not impound water. The fords must also allow
for maintenance of normal stream flows.
(10) Culvert crossings must:
(a) Be limited to 75 feet in length. This
limit may not be exceeded within a half-mile length of the stream or within the
length of stream controlled by the applicant, if less;
(b) Follow the alignment and grade of the
existing stream channel where possible. On perennial streams the culvert's
gradient may not exceed 1%;
(c)
Have the bottom of the entire culvert installed at or below stream bed
elevation, except for additional culverts at the same crossing;
(d) Where two or more culverts are installed,
be offset in order to concentrate low flows into the culvert within the natural
channel;
(e) Be seated on firm
ground, or on geotextiles, logs or other materials used to stabilize the
ground;
(f) Be covered by soil to a
minimum depth of 1 foot or according to the culvert manufacturer's
specifications, whichever is greater;
(g) Have the soil compacted at least halfway
up the side of the culvert; and
(h)
Have the inlet and outlet ends stabilized by riprap in accordance with Section
8 Shoreline stabilization standards
to avoid erosion of material around the culvert.
NOTE: For guidance on riprap installation, consult the Maine
Erosion and Sediment Control BMPs, dated March 2003. This handbook and other
references are available from the DEP.
(11) Wheeled or tracked equipment may not
operate in the water. Equipment operating on the shore may, where necessary,
reach into the water with a bucket or similar extension. Equipment may cross
streams on rock, gravel or ledge bottom.
(12) Work below the normal high water line
must be done during periods of low water level or flow.
(13) If the crossing involves trenching or
disturbance of substrate in a river, stream or brook between October 2 and July
14, the activity must occur during the time period approved by the DEP. The
approved time period may be the time period proposed by the applicant or an
alternative time period approved by the DEP. An alternative time period will be
required where it appears an unreasonable impact on water quality or fisheries
may result at the point of crossing or immediately downstream of the crossing.
The applicant will be notified by the DEP within 14 days if an alternative time
period, other than the one proposed by the applicant, is required for
constructing the crossing.
(14) If
work is performed in a river, stream or brook that is less than three feet deep
at the time of the activity and at the location of the activity, the applicant
must provide for temporary diversion of flow to the opposite side of the
channel while work is in progress.
(a)
Diversion may be accomplished by placing sandbags, timbers, sheet steel,
concrete blocks, 6+ mil polyethylene or geotextiles from the bank to midstream
on the upstream side of the activity. No more than two-thirds (2/3) or 25 feet
of stream width, whichever is less, may be diverted at one time.
(b) Any material used to divert water flow
must be completely removed upon completion of the activity, and the stream
substrate must be restored to its original condition.
(c) A pump may be operated, where necessary,
for a temporary diversion. The pump outlet must be located and operated such
that erosion or the discharge of sediment to the water is prevented.
(15) All wheeled or tracked
equipment that must travel or work in a vegetated wetland area must travel and
work on mats or platforms in order to protect wetland vegetation.
(16) All excavated material must be
stockpiled either outside the wetland or on mats or platforms. Hay bales or
silt fence must be used, where necessary, to prevent sedimentation.
(17) The use of untreated lumber is
preferred. Lumber pressure treated with chromated copper arsenate (CCA) may be
used only if necessary and only if use is allowed under federal law and not
prohibited from sale under 38 M.R.S.A. §1682, and provided it is cured on
dry land in a way that exposes all surfaces to the air for a period of at least
21 days prior to construction. Wood treated with creosote or pentachlorophenol
may not be used where it will contact water.
D.
Definitions. The following
terms, as used in this chapter, have the following meanings, unless the context
indicates otherwise:
(1)
Cross-sectional
area. The cross-sectional area of a stream channel is determined by
multiplying the stream channel width by the average stream channel depth. The
stream channel width is the straight line distance from the normal high water
line on one side of the channel to the normal high water line on the opposite
side of the channel. The average stream channel depth is the average of the
vertical distances from a straight line between the normal high water marks of
the stream channel to the bottom of the channel.
(2)
Crossing. Any activity
extending from one side to the opposite side of a protected natural resource,
or to an island or upland within a protected natural resource whether under,
through or over that resource. Such activities include, but are not limited to
roads, fords, bridges, culverts, utility lines, water lines, sewer lines and
cables, and the clearing and removal of vegetation necessary to install and
maintain these crossings.
(3)
Fill.
a. (verb) To put into or
upon, supply to, or allow to enter a water body or wetland any earth, rock,
gravel, sand, silt, clay, peat, or debris;
b. (noun) Material, other than structures,
placed in or adjacent to a water body or wetland.
(4)
Ford. A permanent crossing
of a stream utilizing an area of existing, non-erodible substrate of the
stream, such as ledge or cobble, or by placing non-erodible material such as
stone or geotextile on the stream bottom.
(5)
Perennial watercourse. A
river, stream or brook depicted as a solid line on the most recent edition of a
United States Geological Survey 7.5 minute series topographic map, or if not
available, a 15 minute series topographic map.
(6)
Riprap. Heavy,
irregularly-shaped rocks that are fit into place, without mortar, on a slope.
Square or rectangular rocks with flat faces, such as quarry stone or
manufactured blocks, do not qualify as "irregularly-shaped".
(7)
Used for navigation. Those
rivers, streams or brooks used by motorized watercraft.