Chapter 61 - STATE BOARD OF EDUCATION RULES FOR MAJOR CAPITAL SCHOOL CONSTRUCTION PROJECTS
Section 071-61-2 - MAJOR CAPITAL SCHOOL CONSTRUCTION PROJECT FLOW CHART, APPLICATION FORM AND SUBMISSION DEADLINES
Current through 2024-13, March 27, 2024
1. Categories of School Construction Projects
2. Major Capital School Construction Project Flow Chart
Each SAU developing a school construction project shall follow the steps in the order in which they are outlined on the Major Capital School Construction Project Flow Chart.
3. Application Form
Each SAU seeking state funding for a proposed school construction project shall submit a completed application form to the Department. Application forms are available from the Department. All parts of the application must be completed.
4. Submission Deadlines
If a Major Capital School Construction project is to be considered for a given rating cycle, a completed application must be received by the Department by the date established by the Department.
5. Waivers
One or more of the requirements of any provision of this Chapter may be waived under any of the following conditions:
The State Board will provide in writing its reasons for granting or denying a waiver request.