A. Drainage parts shall be installed only by a licensed installer or a plumber licensed by the Maine Plumbers' Examining Board.

B. All drainage parts shipped loose with the home shall be installed according to the manufacturer's instructions.

C. All other drainage shall be installed in compliance with the Maine State Internal Plumbing Code as adopted by the Maine Plumbers' Examining Board.

D. The main drain line shall be connected to the site's sewer hook-up using an elastomeric coupling, acceptable under the Maine State Internal Plumbing Codeadopted by the Maine Plumbers' Examining Board, as shown in the figure to this section:

Figure to Subchapter J, Section II - Connection to Site Sewer

Click here to view Image

Disclaimer: These regulations may not be the most recent version. Maine may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.