Section 385-890-B-II - Installation of Manufactured Homes in Flood Hazard Areas
Current through 2024-38, September 18, 2024
A. Definitions
Except to the extent otherwise in Subchapter A, the terms used in this subchapter are as defined in 44 CFR 59.1 of the National Flood Insurance Program (NFIP) regulations.
B. Applicability
The provisions of this section apply to the initial installation of new manufactured homes located wholly or partly within the flood hazard area.
C. Pre-Installation Considerations
Prior to the initial installation of a new manufactured home, the installer is responsible for determining whether the manufactured home site lies wholly or partly within a special flood hazard area as shown on the LAHJ's Flood Insurance Rate Map, Flood Boundary and Floodway Map, or Flood Hazard Boundary Map, or if no LAHJ, in accordance with NFIP regulations.If so located, and before an installation method is agreed upon, the map and supporting studies adopted by the LAHJ must be used to determine the flood hazard zone and base flood elevation at the site.
D. General Elevation and Foundation Requirements
Manufactured homes located wholly or partly within special flood hazard areas must be installed on foundations engineered to incorporate methods and practices that minimize flood damage during the base flood, in accordance with the LAHJ, 44 CFR 60.3(a) through (e) and other provisions of 44 CFR referenced by those paragraphs.
Refer to FEMA 85/September 1985, Manufactured Home and Installation in Flood Hazard Areas (incorporated by reference).