Section 672-11-2 - Administering Agency
Universal Citation: 01 ME Code Rules ยง 672-11-2
Current through 2024-38, September 18, 2024
A. Department of Environmental Protection. The Department of Environmental Protection shall administer the permit process for a hydropower project that:
(1) is located wholly or partly within an
organized municipality not served by LUPC; or
(2) uses tidal or wave action as a source of
electrical or mechanical power, regardless of the hydropower project's
location.
B. Maine Land Use Planning Commission. The Maine Land Use Planning Commission shall administer the permit process for a hydropower project that is located wholly within the State's unorganized and deorganized areas as defined by 12 M.R.S. §682(1), and that does not use tidal or wave action as a source of electrical or mechanical power.
Disclaimer: These regulations may not be the most recent version. Maine may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.