A. The Flood Control Project Evaluation Committee will review applications between October 1 and the following April 1. During the review period, the Joint Legislative Committee on Transportation, Highways, and Public Works will conduct public hearings to solicit comments on projects being considered for funding and will determine the venue for the hearings.
B. During this time, the Evaluation Committee will also receive from the Joint Legislative Committee on Transportation, Highways, and Public Works a projected funding level for the construction program of the coming year.
C. Based on the information gathered at the public hearings and the application evaluations, the Evaluation Committee will submit a list of recommended projects to the Joint Legislative Committee, on the basis of the distribution of funds described below.
AUTHORITY NOTE: Promulgated in accordance with R.S. 38:90.1 et. seq.